Heemskirk Tin project, Tasmania.

Client
Stellar Resources.

Project Description
Heemskirk Tin has a total resource of 6.28-million tonnes, grading 1.14% tin.

A positive prefeasibility study (PFS) on the Heemskirk Tin has demonstrated the technical and economic viability of the project.

The PFS is based on a 600 000 t/y under-ground mining operation at Heemskirk, with an initial mine life of seven years and the potential to expand once additional drilling within the current Severn resource is complete.

Mining will be undertaken on four orebodies – Upper and Lower Queen Hill, Severn and Montana.

Mining will be a combination of long-hole open stoping and cut-and-fill methods.

Processing will be at a rate of 600 000 t/y for all orebodies except Lower Queen Hill, which will be processed at an estimated 460 000 t/y. There is lower throughput when treating Lower Queen Hill ore because the ore is not amenable to preconcentration by heavy-media separation of barren gangue prior to conventional treatment.

Value
Total preproduction capital is estimated at $113.9-million.

Duration
Not stated.

Latest Developments
The development of the Heemskirk Tin project from PFS stage to definitive feasibility study will include:
• drilling to further define the existing mineral resource to measured and indicated status;
• the recovery of core from the four orebodies for further metallurgical testing and variability;
• investigations;
• core sampling to test the acid-generating capability of ore and waste;
• the collection of geotechnical data and bore-hole water samples to investigate hydrology;
• process plant cost and performance optimisation, based on further metallurgical testing;
• the completion of flora, fauna, aboriginal heritage and archaeology surveys, as well as a community impact report;
• the submission of a development plan and environmental management plan; and
• the preparation of an engineering definition study/feasibility study.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Stellar resources, tel +61 3 9618 2540 or fax +61 3 9649 7200.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.079 0.825s - 147pq - 2rq
Subscribe Now