Hastings cuts costs at Yangibana

29th July 2020

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Rare earths developer Hastings Technology Metals has reduced the capital cost expectations at its Yangibana project, in Western Australia, by some A$68-million.

The cost savings come as the company pursues a decoupled processing strategy and a relocation of the hydrometallurgical plant to the Pilbara.

The reduction in the capital cost resulted from the elimination of a 114-km gas pipeline as well as a 40% reduction in on-site water abstraction and power requirements, Hastings told shareholders on Wednesday.

“The Yangibana rare earths project is proving to be an economically strong project even in this challenging Covid-19 environment. In line with our pursuit of continuous improvement in the project’s robustness, the Hastings leadership saw an opportunity to optimise and improve the proposed project layout and further reduce the required capital expenditure,” said executive chairperson Charles Lew.

‘The decision to consider a de-coupling of Yangibana’s processing set-up not only allows us to reduce the overall project’s capital cost, but deliver significant benefits, including streamlining operating expenditure associated with logistics arrangement and other associated infrastructure costs, alongside creating significant residential job opportunities in regional Western Australia.”

Detailed capital and logistics costs of the location for the hydrometallurgical plant have started, with Lew saying there would be a need for some additional costs through duplication of equipment and services for the new location.

Transportation of a beneficiated concentrate from the mine site to the new plant location would also be required, however, these costs would be offset by eliminating the need to transport large volumes of sulphuric acid, caustic soda and other chemical reagents to the mine site.

The proposed hydrometallurgical plant location has an already established Native Title Agreement and does not impact on any cultural heritage sites, the company added.

The one-million-tonne-a-year Yangibana operation is expected to produce some 15 000 t/y of mixed rare earths carbonate, and about 8 850 t/y of total rare earth oxides, with Hastings previously estimating a capital spend of A$517-million to bring the project on line.

Edited by Creamer Media Reporter

Comments

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.089 0.138s - 162pq - 2rq
Subscribe Now