Gudai-Darri (formerly Koodaideri) iron-ore mine, Australia – update

24th June 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gudai-Darri (formerly Koodaideri) iron-ore mine.

Location
Pilbara, Western Australia.

Project Owner/s
Rio Tinto.

Project Description
Gudai-Darri will be Rio Tinto’s most technologically advanced mine.

The investment is underpinned by an orebody – more than 20 km long and 3 km wide – of high-quality Brockman ore. 

The operation has been designed to use an increased level of automation and digitisation, helping to deliver a safer and more productive mine, which is expected to be Rio Tinto’s lowest-cost contributor to its industry-benchmark Pilbara Blend product.

Using digital assets, advanced data analytics and automation, Rio Tinto expects to significantly enhance the operation and maintenance of this new mine.

Phase 1 of the project will help sustain Rio Tinto’s existing production capacity by replacing depletion elsewhere in the system. The project will increase the higher-value lump component of the Pilbara Blend, subject to market conditions, from the current average of about 35% to about 38%. This first phase of Gudai-Darri will have a 43-million-tonne-a-year capacity, underpinning production of the Pilbara Blend. 

The project incorporates a processing plant and infrastructure, including a 166 km rail line connecting the mine to Rio Tinto’s existing network. Mine infrastructure, an airport, mine support facilities and accommodation for employees will also be built.

The proposed Phase 2 expansion could increase capacity from the Gudai-Darri production hub to 70-million tonnes a year and beyond.

Potential Job Creation
About 600 permanent jobs are expected to be created once the mine is operational.

To date, the project has awarded local businesses – including Pilbara-, Pilbara Aboriginal- and Western Australia-based businesses – contracts valued at more than A$1.1-billion, supporting about 2 000 jobs in the construction phase.

Potential Job Creation
The development of Gudai-Darri supported more than 3 000 jobs during the construction and design phase. The mine will support around 600 ongoing permanent roles. 

Net Present Value/Internal Rate of Return
The project is expected to deliver an internal rate of return of 20% and capital intensity of about $60/t/y.

Capital Expenditure
$3.1-billion.

Planned Start/End Date
The project was approved in November 2018. Rio Tinto expects production to ramp up in 2022.

Latest Developments
Rio Tinto officially commissioned the Gudai-Darri mine on June 21, 2022, marking its most technologically advanced mine to date.

The project features some of the most advanced technology, including a robotic ore-sampling laboratory that provides visibility of the ore grades out of the mine within minutes. 

Autonomous trucks, trains and drills, which are standard across many of Rio Tinto's Pilbara mines, are also on site, along with a digital replica of the processing plant, which enables teams to quickly test different situations digitally before implementing. 

Rio is also building a 34 MW solar farm consisting of 83 000 solar panels that will power one-third of Gudai-Darri's electricity needs; completion is expected in August 2022.   

Key Contracts, Suppliers and Consultants
NRW Holdings (bulk earthworks and prestrip contract).

Contact Details for Project Information
Rio Tinto, email media.enquiries@riotinto.com.

 

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.056 0.896s - 127pq - 2rq
Subscribe Now