Finders starts the hunt for financing
PERTH (miningweekly.com) – ASX-listed Finders Mines is hunting for financing following the completion of a revised bankable feasibility study (BFS) for its Wetar copper project, in Indonesia.
The company previously revealed that the revised BFS had resulted in a A$34-million decrease on capital spend expectations, reducing capital costs to around A$133-million.
The revised design incorporated a new solvent extraction electrowinning plant, which is a single-stage 25 000 t/y plant based on an extension of the existing 16 000 t/y ex-Whim Creek plant.
The single-stage design reduced the construction cost and time compared with the previous two-stage plant design.
Finders said on Wednesday that at full production, Wetar would deliver some 28 000 t/y of copper cathode, with full capacity expected to be reached within 15 months of the start of on-site construction.
Full production was currently earmarked for the third quarter of 2015.
Life-of-mine copper production was estimated at 155 000 t, over a planned 10.5-year production period.
“The Wetar copper project is a first quartile operating cost project driven by the high-grade and low openpit strip ratio,” said MD Barry Cahill.
He added that the revised project cost left Finders well placed as one of the few ASX-listed copper companies moving into production.
The project was expected to have a net present value of A$195-million, at a copper price of A$6 000/t and an internal rate of return of 52%.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation