Name of the Project
Fekola gold mine expansion project.

Location
Mali.

Project Owner/s
B2Gold.

Project Description
Fekola has total mineral reserves of 56.73-million tonnes grading 1.74 g/t gold and indicated resources of 147.6-million tonnes grading 1.33 g/t gold, as well as inferred resources of 85.51-million tonnes grading 1.12 g/t of gold.

The project comprises the Fekola mine, with the Medinandi permit hosting the Fekola and Cardinal zones; and Fekola Regional, with the Anaconda Area hosting the Bantako, Menankoto, Bakolobi and Dandoko permits.

B2Gold is progressing an engineering study of a Fekola Regional standalone mill and oxide processing facilities, expected to be located on the Anaconda Area.

Construction of a standalone oxide mill would constitute Phase 2 of the Fekola Regional development plan. The engineering study will be based on processing four-million tonnes a year of saprolite and transitional (oxide) resources.

The optimization study analysis indicates that the combined Fekola mine and Fekola Regional processing facilities could produce more than 800 000 oz/y of gold from the Fekola Complex, subject to the delineation of additional mineral resources and development, the completion of feasibility studies and the receipt of all necessary regulatory approvals and permits.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Not stated.

Latest Developments
From January 2022 until March 31, 2023, B2Gold has completed about 120 000 m of drilling at the Anaconda Area, which has included infill drilling to upgrade a significant portion of the inferred oxide resources to the indicated category, as well as extending oxide and sulphide resources in the area.

An updated Anaconda Area mineral resource estimate is under way and scheduled to be completed by the end of the second quarter of 2023. Consequently, to allow for the incorporation of this updated mineral resource estimate into the engineering study, results of the study are now expected in the fourth quarter of 2023. 

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
B2Gold, tel +1 604 681 8371 or email investor@b2gold.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.056 1.028s - 147pq - 2rq
Subscribe Now