JOHANNSBURG (miningweekly.com) – Aim-listed Gem Diamonds has warned that it may need to reassess its operating cost guidance for the full year, as a result of the impact of extreme weather conditions on its Letšeng mine, in Lesotho.

Recent excessive snow falls and severe winds have limited access to the mine and damaged overhead power lines.

Standby generators installed at the mine have been used to mitigate some of the impact, allowing the processing plants to operate at reduced rates.

The Lesotho Electricity Company is carrying out repairs to damaged overhead power lines and external power supply to the mine is expected to be fully restored in the short term.

However, Gem expects the power interruptions to impact ore tons treated and operating costs for the full-year, but says recovered carats should not be materially affected, owing to the strong operational performance in the first half of the year.

The company will announce its results for the six months to June 30 on August 17.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 1.439s - 140pq - 2rq
Subscribe Now