Euro Sun details plan for Romania mine

20th February 2019

By: Mariaan Webb

Creamer Media Contract Publishing Editor

     

Font size: - +

TSX-listed Euro Sun Mining has completed a preliminary economic assessment (PEA) for the initial phase of development at the Rovina Valley gold/copper project, in Romania, detailing plans to produce 108 000 oz/y of gold and 13.3-million pounds a year of copper, or 139 000 oz/y gold equivalent.

The PEA focuses on the exploitation of the Colnic openpit, which will produce 1.67-million gold equivalent ounces over 12 years, at an all-in sustaining cost of $752/oz of gold equivalent.

Besides Colnic, which is the first stage of development at the project, Rovina Valley also consists of the Rovina gold/copper deposits, which are amenable to openpit development, and the Ciresata gold/copper deposit, suitable for underground development.

All three deposits are in close proximity and mill feed will be treated at a central facility.

Euro Sun CEO Scott Moore said on Wednesday that Colnic would form the foundation of a multi-decade operation with the expectation of bringing the Rovina pit on line using pre-installed infrastructure followed by the Ciresata deposit.

Colnic is an at-surface openpit deposit containing only 28.6% of the total measured and indicated resources at the Rovina Valley project.

The PEA for the Colnic openpit calculated a pre-tax net present value of $218.1-million with an internal rate of return of 15.4%. The initial capital cost is estimated to be $339.7-million.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.065 1.217s - 140pq - 2rq
Subscribe Now