Eskom says New Largo coal supply talks with Anglo have resumed

5th December 2014

By: Terence Creamer

Creamer Media Editor

  

Font size: - +

Electricity utility Eskom says it and Anglo American concluded a memorandum of understanding (MoU) on November 2 that maps out the process to be followed to enable the parties to conclude a final coal supply con- tract for the Kusile power station, which is cur-rently being built in Mpumalanga province.

The MoU focuses on the New Largo colliery, a project owned by Anglo American Inyosi Coal, which is a black economic-empowerment (BEE) company held by Anglo American (73%) and the Inyosi Consortium (27%).

The project will comprise a new opencast mine, as well as a conveyor from the existing Phola processing plant to the 4 800 MW Kusile power station.

Eskom executive for group capital Dan Marokane last week said that talks had resumed with Anglo American Inyosi Coal and suggested that both sides were “comfortable” with the process outlined in the MoU.

The focus, he said, was on dealing with the unresolved issues standing in the way of the conclusion of a long-term coal supply agreement.

Work was under way to iron out “technical issues” relating to the mine plan, which would inform the cost of the project and, in turn, the commercial terms of the eventual supply agreement.

The MoU emerged after a high-level intervention between Eskom and Anglo executives in London earlier this year, after relations broke down, reportedly as a result of Eskom’s 51% BEE ownership stipulations for the project.

Marokane confirmed that the initial 800 MW Kusile Unit 1, which was scheduled for grid synchronisation by the end of 2015 or early 2016, would receive coal from third-party suppliers.

Contracts had already been concluded with those suppliers, with the contracted coal currently being delivered to other power stations within the Eskom fleet, while Kusile project work continued.

Marokane reported that teams were being “remobilised” in line with the MoU and that efforts would be made to “claw back” time that had been lost, while still ensuring that Eskom paid a fair price for the coal.

CEO Tshediso Matona argued that the New Largo issue should be delinked from the so-called “coal cliff” dilemma facing the utility, which related to the need to replenish long-term supply contracts after the existing contracts had expired.

He said there was an “urgent need” for Eskom and the coal industry to resolve the matter so as to ensure security of coal supply to the power stations.

“These are big issues that require a systematic engagement with the coal industry,” Matona argued.

Themba Mkhwanazi, CEO of Anglo American’s coal business in South Africa and chairperson of Anglo American Inyosi Coal, says: “This MoU is a culmination of months of negotiations and enables the continued implementation of the New Largo project. The purpose of this MoU is to affirm that, while both Anglo American Inyosi Coal and Eskom are broadly aligned regarding Eskom’s empowerment imperatives, we need to establish a framework within which we can cooperate and achieve a mutually beneficial outcome.”

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Axiom Hydraulics
Axiom Hydraulics

Axiom Hydraulics is a trusted leader in South Africa’s hydraulic industry, delivering world-class components, systems, and engineering expertise...

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.04 0.798s - 122pq - 2rq
Subscribe Now