https://www.engineeringnews.co.za

Eskom aims to buy 500 MW more from IPPs ahead of Medupi, Kusile ramp-ups

20th June 2014

By: Terence Creamer

Creamer Media Editor

  

Font size: - +

State-owned electricity utility Eskom will issue a tender soon for the procurement of an additional 500 MW of capacity from private generators as part of a larger intervention to ensure supply security ahead of the introduction of new capacity from the Medupi, Kusile and Ingula projects.

Interim CEO Collin Matjila reported this month that 598 MW had already been contracted with outside suppliers, including the Kelvin power station (150 MW), the Aggreko temporary power plant in Mozambique, as well as a number of short-term purchases from independent power producers (IPPs) and municipalities.

All the contracts will remain in force until the end of April 2015, by which time the much-delayed Medupi Unit 6 should be ramped up to full capacity.

Progress in dealing with defective boiler welds, together with the recent factory-acceptance-test approvals for the boiler protection system software, has given Eskom confidence that the first 800 MW unit will be synchronised to the grid in December. The unit, which is the first of six, will then be ramped up to full production during the course of the first quarter of 2015.

However, Matjila cautioned that the electricity system would remain under pressure until a number of Medupi and Kusile units had been commissioned, with Kusile Unit 1 still scheduled for grid synchronisation during the course of the 2015/16 financial year. Therefore, Eskom would be pursuing other supply- and demand-side interventions in a bid to bolster its reserve margin.

Group executive for sustainability Dr Steve Lennon said Eskom would seek to tap additional supply from the private sector, including from companies that had immediate cogeneration capacity, as well as those able to aggregate standby-generator capacity that had been introduced by a number of companies since the rotational load-shedding crisis of 2008.

He said an enquiry would be released soon and that it hoped to conclude contracts with suppliers before the end of the year. The tender will seek short-term capacity to the end of April 2015, but would also include the flexibility for two- or three-year contract periods.

That said, the utility remained under major financial stress and would, thus, also need to consider the best way of funding the new capacity, while also ensuring the purchases were affordable. For this reason, volume and price caps could be included in the contracts.

However, when compared with the cost of operating the open-cycle gas turbines (OCGT), Lennon was convinced that the National Energy Regulator of South Africa would view the additional IPP costs as having been “prudently incurred” – Eskom would then be entitled to use the Regulatory Clearing Account mechanism to recoup the expenses.

There is also a big focus currently on reducing partial losses, which Eskom believes can add 1 000 MW of additional supply-side capacity as the country enters the high-demand winter period when demand is expected to peak at 36 000 MW sometime in July.

The utility has also set a 1 500 MW demand-side target, comprising 230 MW of demand market participation from large industrial consumers, 700 MW from integrated demand management programmes and a further 200 MW from other initiatives.

It has also sustained its 2 000 MW interruptible contract with BHP Billiton’s Hillside and Mozal aluminium smelter, but has been able to improve flexibility in the manner in which these can be deployed.

Developments in the strike-afflicted platinum belt are also being closely monitored, with Eskom currently supplying about half of the 800 MW traditionally drawn by the mines in the North West province.

Group executive for transmission Mongezi Ntsokolo said it would be critical to maintain close communication with the platinum miners to ensure that capacity is available if and when the platinum mines began reopening. In the meantime, it would use the space created by the sector’s lower demand to continue with critical maintenance.

Matjila stressed that the attention given to maintenance over the last two years was beginning to bear some fruit, with Eskom planning to taper its winter maintenance programme from 2 000 MW in 2013 to around 1 600 MW between June and the end of August.

Higher availability is also expected to enable it to rely less on the expensive OCGT plants than has been the case in winter last year, with R1-billion having been spent on diesel in the first two months of the current financial year, as compared with the R1.4-billion spend in April and May of 2013.

Nevertheless Matjila warned that, in the context of a tight system, any significant event could result in load-shedding, which remained a “last resort” measure that would only be used should there be a risk of a total blackout.

South Africa had its most recent load-shedding event on March 6, 2014, which arose as a result of a breakdown in the supply of coal to the Kendal power station, in Mpumalanga.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 
Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.062 1.132s - 122pq - 2rq
Subscribe Now