Data centre construction project, Ireland
Name of the Project
Data centre construction project.
Location
Dublin, Ireland.
Client
Baylite Company, a subsidiary of the Kuok Group.
Project Description
The project involves the construction of a data centre for a US data company.
The centre will be built within an existing 11 000 m2 warehouse and will include 5 200 m2 of Tier III technical data space across two storeys.
The facility will offer 22 MW of critical information technology load using state-of-the-art technologies to cater to high-density customer requirements. It will deploy a market-leading fresh-air, evaporative cooling technology, which will significantly decrease energy and water consumption, compared with the typical performance of a data centre of this size.
The facility will comprise six self-contained data halls, all capable of subdivision for maximum flexibility and each with its own dedicated power and cooling systems.
Jobs to Be Created
Not stated.
Value
Not stated.
Duration
The first phase of the data centre will be handed over in June 2017, with completion scheduled for January 2018.
Latest Developments
Bouygues has been awarded the turnkey construction contract for the development of the data centre.
The contract is valued at €100-million.
Key Contracts and Suppliers
Bouygues (turnkey construction contract).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Kuok Group, tel +65 6733 3600, fax +65 6738 9300 or email corporate@kuokgroup.com.sg.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation