Crucea North wind farm project, Romania.

Client
The project will be developed by Crucea Wind Farm, a 100%-owned subsidiary of Steag.

Project Description
The project involves the development of a 99 MW wind farm, with an option to expand to 108 MW.

It will comprise 33 wind turbines (36 turbines after expansion) of 3 MW each.

It will include:
• the construction of a 33/110 kV project substation, located within the wind farm site boundary;
• the construction of a 400/110 kV new transformer station, Stupina 2, with one 250 MVA transformer, which will be connected to the existing Stupina 110/400 kV transformer station;
• a temporary construction compound within the wind farm site boundary, which will be removed once the construction of the wind farm is complete;
• a concrete foundation for each turbine;
• crane pads;
• the upgrade of an estimated 45 km of existing agricultural service roads and the construction of about 6 km of new access roads to the turbines;
• the construction and operation of about 43 km of underground medium-voltage (33 kV) electrical connection lines to link the turbines and the 33/110 kV project substation within the wind farm site boundary;
• the construction and operation of about 8.8 km of underground high-voltage transmission lines (110 kV) from the 33/110 kV project substation to the 400/110 kV Stupina 2 transformer station; and
• the construction and operation of about 150 m of underground high-voltage transmission lines (400 kV), connecting the 400/110 kV Stupina 2 transformer station to the power distribution grid, owned by State-owned power company Transelectrica, through the existing 110/400 kV Stupina transformer station.

Value
Implementation will cost about €192-million.

Duration
Not stated.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Steag, tel +49 201 801 00 or fax +49 201 801 6388.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.084 1.107s - 146pq - 2rq
Subscribe Now