Creecy moves ahead with plan to declare coal and gold towns as renewables zones
South Africa's approved and proposed REDZs relative to the existing power corridors
Photo by CSIR
The seven power corridors
Environment, Forestry and Fisheries Minister Barbara Creecy has called for public comment on government’s intention to add three more Renewable Energy Development Zones (REDZs) to the eight that have already been proclaimed for the purpose.
Renewable-energy projects located within the boundaries of a REDZ are beneficiaries of streamlined environmental authorisation processes.
In a Gazette notice dated July 17, Creecy confirmed that government aimed to declare Emalahleni, in Mpumalanga, and Klerksdorp, in the North West, as REDZs 9 and 10 respectively, thereby officially earmarking the coal and gold towns as regions in which large-scale solar photovoltaic (PV) facilities should be deployed.
In addition, Beaufort West, in the Western Cape, had been earmarked as REDZ 11, with the Gazette notice indicating that the area is suitable for large-scale wind and solar PV facilities.
The three proposed REDZs were identified following a Phase 2 Strategic Environmental Assessment (SEA) for the roll-out of utility-scale wind and solar PV developments in South Africa conducted by the department and the Council for Scientific and Industrial Research.
Following a Phase 1 SEA, REDZs were proclaimed in Overberg, Komsberg, Cookhouse, Stormberg, Kimberley, Vryburg, Upington and Springbok.
The REDZs also represent priority areas for investment in the electricity grid, regarded as the main enabler of higher levels of renewables penetration in South Africa.
In parallel, therefore, Creecy has also called for comment on government’s intention to declare seven corridors as strategically important for the planning and development of electricity transmission and distribution infrastructure.
As with the REDZs, the corridors were identified and assessed through SEAs for electricity grid infrastructure in South Africa and the expansion of that infrastructure through corridors.
Also published for comment by the Minister was a notice of her intention to declare strategic gas pipeline corridors, which were identified following a SEA completed in 2019.
Again, a 30-day period has been allocated, from July 17, for the receipt of public comment.
It is currently anticipated that the new REDZs, as well as the corridors, could be operational by the end of 2020.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation