Cape Town International Airport upgrade, South Africa
Name of the Project
Cape Town International Airport (CTIA) upgrade.
Location
Cape Town, Western Cape, South Africa.
Project Owner/s
Airports Company South Africa (ACSA).
Project Description
The CTIA has several key infrastructure projects planned over the next five years.
The upgrade will include:
• the refurbishment of the domestic arrivals terminal, which will include an express exit route available to passengers who only have ‘carry on’ luggage and do not need to collect bags, as well as a new, bigger meet-and-greet area and an expanded retail area.
• the expansion of the international terminal, which will include the expansion of the check-in area for international passengers, the addition of two baggage collection carousels and the reconfiguration of the security, customs, passport control and meet-and-greet areas.
• a new realigned runway, which will allow for the expansion of the terminals in future. CTIA will also construct parallel and rapid exit taxiways. The realigned runway will be 3 500 m long.
The new runway will allow for the number of landings and departures per hour to inceease from 30 to 45 aircraft movements.
It will also enable the airport to handle new-generation large aircraft such as the Boeing 747-800 or the A380s.
Potential Job Creation
Not stated.
Capital Expenditure
The upgrade will involve an investment of about R7.5-billion over the next five years, including an estimated R688-million for the new domestic arrivals terminal, R2.8-billion for the expansion of the international terminal and R3.93-billion for the realignment of the runway.
Planned Start/End Date
The refurbishment of domestic arrivals terminal is expected to start construction in early 2020 and take 30 months to complete.
If all goes according to plan, the expansion of the international terminal will start towards the end of 2019, with the facility to be commissioned in December 2023.
Construction of the realigned runway is expected to start in early 2020. ACSA envisions a 24-month construction period and a six-month commissioning period.
Latest Developments
A professional team has been appointed and is completing the tender documentation for the expansion of the international terminal.
The project for the realigned runway is in the tender preparation phase.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
CTIA, tel +27 21 937 1200.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation