Botswana peaking-to-midmerit power plant

19th September 2008

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Botswana peaking-to-midmerit power plant.

Project Description
The project will see the development of a peaking-to-midmerit power plant with a minimum capacity of 250 MW.

The project includes the production of coal-bed methane and the construction of a power plant. Of the 250 MW, 90 MW will be supplied to the 220-kV Orapa substation, in Botswana, of which 45 MW will be supplied to the mining industry. The remaining 200 MW to 225 MW to be generated will be supplied to the rest of the country.

Value
$400-million.

Duration
The commercial operation of the plant is expected by June 2010.

Client
The project is an initiative by the Botswana Power Corporation.

Key Contracts and Suppliers
Karoo Sustainable Energy (KSE) (independent power producer (IPP)) and Group Five and Single Destination Engineers, and General Electric (gas turbines).

Latest Developments
Botswana-based company KSE has been appointed as the IPP to develop the plant (engineering, procurement and construction management (EPCM) contract).

South African engineering and construction company Group Five's power division and local engineering firm Single Destination Engineers has been awarded the EPCM.

KSE will be awarding contracts for the 200 km of gas pipeline, the compressor stations and all the delivery systems before year-end.

The project is expected to create 200 to 250 jobs during the different phases of construction. For the first two years, technicians from General Electric, which is supplying the gas turbines for the project, will be employed on operations and maintenance until the necessary skills have been developed and passed down to KSE's Botswana engineers, who will then be responsible for all operations.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
KSE, tel +267 395 3609 or fax +267 392 4949.
 

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.054 0.937s - 145pq - 2rq
Subscribe Now