PERTH (miningweekly.com) – Commissioning and first production from the Boonanarring mineral sands project, in Western Australia, remained on track for the fourth quarter of this year, owner Image Resources said.

The company on Tuesday said that construction of the opencut mine started in April, with the exposure of first high-grade ore expected by the end of September.

Site infrastructure has also been installed, and the permanent administration offices have arrived on site and will be commissioned in August.

Image told shareholders that the project, which is fully funded, remains within 2% of the total budgeted cost.

The Boonanarring deposit is expected to deliver 1.1-million tonnes of heavy mineral concentrate and the Atlas deposit an additional 711 000 t. The Boonanarring deposit is estimated to have an initial mine life of five years, after which mining will move to the Atlas deposit, which will add a further three years to the overall mine life.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.064 0.645s - 140pq - 2rq
Subscribe Now