Name of the Project
Bisie tin project.

Location
The project is located in the Mpama North prospect, in North Kivu province, in the Democratic Republic of Congo (DRC).

Client
The Bisie tin project is 82.5%-owned through Alphamin Resources’ DRC registered subsidiary ABM SA; 5%-owned by the DRC government and 14.25%-owned by the Industrial Development Corporation of South Africa.

Project Description
The Bisie project contains two exceptional high-grade deposits – Mpama North and Mpama South – and is one of the highest-grade known tin deposits in the world.

The front-end engineering design (FEED) and control budget estimate (CBE)  have increased proven and probable reserves from 3.52-million tonnes grading at 4.34% tin containing 152 800 t in the 2016 updated feasibility study to 4.67-million tonnes at 3.58% tin containing 167 300 t.

The life-of-mine has also been increased from 12 to 12.5 years.

The completion of the FEED programme and CBE in February this year further confirmed the robust economic metrics and potential of the project, and its development into North Kivu’s first commercial mine and a new premier global tin-producing mine.

The CBE results have illustrated the project’s potential to remain profitable at lower tin prices and increased prices for key consumables.

The fundamental mining method has not changed, but the layout and mine design parameters have changed notably from the updated feasibility study issued in June 2016.

Contractors will mine the Mpama North orebody using proven underground mechanised mining methods to deliver ore to the process plant at an expected rate of 25 000 t/m to 35 000 t/m.

The process design is based on the recovery of tin into concentrate through conventional gravity separation methods. The process plant design capacity has been estimated at between 360 000 t/y and 400 000 t/y.

Jobs to be Created
The project will employ about 700 people during construction and create about 450 permanent local jobs during operations.

Indirect job creation is expected to be far higher than the mine’s direct jobs and can be reasonably expected to achieve the 1:14 ratio of indirect jobs commonly reported in Africa for similar projects, potentially resulting in an additional 6 300 jobs.

Net Present Value/Internal Rate of Return
The FEED and CBE have estimated a net present value, at an 8% discount rate, of $402.2-million and an internal rate of return of 49.1% after tax. Payback has been estimated at 17 months from first production.

This compares with a post-tax net present value, at a 13.54% discount rate, of $167.79-million, and an internal rate of return of 48.4%, with a payback of 23 months in the updated feasibility study.

Value
The peak funding requirement for the project has increased from $124.4-million in the updated feasibility study to $151.43-million in the CBE.

The initial capital costs include the design and development of an access road, an underground mine, the creation of a 64 000 t ore stockpile, a process plant, a tailings storage facility and all associated services required for the operation of the mine.

Duration
The company is aiming to produce its first tin concentrate during the first half of 2019.

Latest Developments
Local earthworks contractor Kongo River, which is responsible for all the project’s earthworks, and mining contractor Reliant Congo, which is responsible for shotcreting and soil nailing, as well as underground mining once the mine is in operation, have made good progress with the project.

The boxcut is nearing completion and cutting of the decline portal for the new underground mine will start soon. The mine’s return airway adit is 120 m in length and has intercepted the orebody and will provide Alphamin with it first actual view of the underground orebody, beyond what it has recorded in previous drill results.

The company has invested about $70-million in the project, with $134-million in capital still needed. Alphamin is reportedly close to signing up $80-million worth of debt financing, which will leave it with $54-million that still needs to be raised.

Key Contracts and Suppliers
Kongo River (earthworks) and Reliant Congo (mining contract).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Alphamin Resources CEO Boris Kamstra, tel +230 269 4166 or email boris.kamstra@alphaminresources.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 1.063s - 147pq - 2rq
Subscribe Now