Beharra silica sands project, Australia
Name of the Project
Beharra silica sands project.
Location
Perpetual Resources.
Project Owner/s
South-east of Geraldton, Western Australia.
Project Description
A prefeasibility study has confirmed that the project will deliver exceptionally strong margins over the initial 32-year mine life. The project has Joint Ore Reserves Committee-compliant in situ probable ore reserves of 64-million tonnes grading 98.6% silicon oxide.
The project envisages production of 1.5-million tonnes a year from a run-of-mine production of two-million tonnes a year.
Total silica sand expected to be produced is estimated at 48-million tonnes.
The project will use simple mining and processing.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an after-tax cash flow net present value, at a 10% discount rate, of A$231-million and an internal rate of return of 55%, with a payback two years.
Capital Expenditure
A startup capital of A$39-million will be required.
Planned Start/End Date
The overall timeline for development, permitting and approval activities is targeting startup of construction in the second quarter of 2022, with the start of mining and processing operations in the fourth quarter of 2022.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
Snowden (ore reserves).
Contact Details for Project Information
Perpetual Resources, email info@perpetualresourceslimited.com.au.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation