Bauxite Hills project, Australia

10th July 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Bauxite Hills project, Queensland, Australia.

Client
Metro Mining.

Project Description
A prefeasibility study (PFS) completed on the Bauxite Hills project has confirmed the project’s attractive economics.

Bauxite Hills comprises two bauxite plateaus (BH 1 and BH 6) situated next to the Skardon river.

The forecast quality and nature of the bauxite is suitable for export as direct shipping ore (DSO).

The PFS indicates that a DSO operation allows for the development of a low-capital and low-operating cost mine, by avoiding significant costs traditionally associated with the production of a beneficiated bauxite product, including reduced infrastructure costs and significantly reduced water and energy. In addition, no tailings dams are required.

Mine operations proposed are simple and will use trucks and front-end loaders. No blasting is required. The bauxite is planned to be hauled to the barge load-out facility at the Skardon river, then transported by barge about 10 km offshore where it will be transshipped into bulk carriers for export to overseas customers.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 15% discount of A$197-million and an internal rate of return of 88%, with capital payback of 1.1 years from first production.

Value
The project’s capital expenditure is estimated at A$27.4-million.

Duration
The project schedule is based on the completion of the approval process and the granting of a mining lease by March 2016, with construction and mine development scheduled to start during the second quarter of 2016 and first production by the fourth quarter of the same year.

Latest Developments
Metro Mining has announced a near fivefold increase in the ore reserves at its Bauxite Hills project. The ore reserve has increased by 398% to 48.2-million tonnes, of which 41.8-million tonnes have been classified as proven and 6.4-million tonnes as probable reserves.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Metro Mining, tel +61 7 3009 8000, fax +61 7 3221 4811 or email info@metromining.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.055 0.573s - 165pq - 2rq
Subscribe Now