Bald Hill lithium plant project, Australia

18th August 2017

By: Creamer Media Reporter

     

Font size: - +

Name of the Project
Bald Hill lithium plant.

Location
The Bald Hill project area is located 50 km south-east of Kambalda, in the Eastern Goldfields of Western Australia.

Client
Tawana Resources and Alliance Mineral Assets Limited (AMAL).

Project Description
The project comprises four mining leases, one mining lease application, 12 exploration licences, eight prospecting licences and one general purpose lease totalling 790 km.

A July 2017 prefeasibility study (PFS) confirmed the technical and financial viability of a low-capital-cost, 1.2-million-tonne-a-year lithium dense media separation (DMS) circuit, adjacent to the existing tantalum processing facility at Bald Hill.

The PFS estimates initial production of 155 000 t/y of spodumene concentrate from the DMS and 260 000 lb/y of tantalum pentoxide from the TPF. Further feasibility work is being undertaken on a lithium fines circuit to treat stockpiled fines and middlings, which has the potential to add to production.

Jobs to be Created
About 200 people will be on site during the peak construction period.

Net Present Value/Internal Rate of Return
The project has an expected internal rate of return of 185%.

Value
A$42.20-million

Duration
The first shipment of lithium concentrate is scheduled for March 2018.

Latest Developments
Tawana and AMAL have executed an engineering, procurement and construction (EPC) contract with the Primero Group. The contract is a lump sum, fixed price contract valued at A$30-million.

Primero mobilised to the site in August 2017, marking the start of construction.

The following construction milestones have been reported:
• Site mobilisation and the start of site works.
• Temporary construction offices have been set up.
• The plant site is 100% cleared and detailed earthworks are in progress.
• Concrete works are in progress and plant feed preparation area is proceeding on schedule.
• About 50% of design has been completed in accordance with the project schedule.
• All major procurement packages have been awarded.
• Fabrication packages awarded.

Key Contracts and Suppliers
Primero Group (EPC).

On Budget and on Time?
The project is on track for commissioning to start in the first quarter of 2018.

Contact Details for Project Information
Tawana investor relations, Phone: +61 8 9489 2600, email: admin@tawana.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

Showroom

Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.862s - 147pq - 2rq
Subscribe Now