Name and Location
Bafokeng Rasimone Platinum Mine (BRPM) North shaft Merensky Phase 3 project, North West, South Africa.

Client
BRPM Joint Venture (JV), comprising Royal Bafokeng Platinum (RBPlat) and Anglo American Platinum (Amplats).

Project Description
The BRPM Phase 3 project is providing further replacement for Merensky production at the North shaft complex through the extension of the existing decline from level 10 to level 15 at the mine boundary.

At steady state, Phase 3 will maintain the production level of North shaft at about 100 000 t/m.

Value
R1.409-billion. Project expenditure to date is R667-million, with a budget of R781-million.

Duration
The project started in November 2010 and is scheduled for completion in the third quarter of 2017.

Latest Developments
At the end of June 2014 the project was 66% complete against a planned completion of 59%. Development is 1 237 m ahead of schedule, with 5 945 m completed against a planned 7 182 m.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Overall project completion is forecast to be four months ahead of schedule in 2017.  The project remains well below budget, with an estimated cost at
completion of R1.29-billion.

Contact Details for Project Information
RBPlat communications manager Kea Kalebe, tel +27 14 573 1487, fax +27 86 219 5131 or email kkalebe@bafokengplatinum.co.za.
Amplats corporate communications Mpumi Sithole, tel +27 11 373 6246, fax +27 11 373 5846 or email  Mpumi.sithole@angloamerican.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Aluminium Federation of South Africa
Aluminium Federation of South Africa

The Aluminium Federation of South Africa (AFSA), is the voice of the South African aluminium industry.

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.903s - 147pq - 2rq
Subscribe Now