The Proyecto Riotinto mine, in Spain, expects to reach its expanded throughput rate of 15-million tonnes a year by the end of 2019, despite delays to increased electricity supply.

The expansion project reached full mechanical completion on August 19 and has started ramping up. However, the increase in throughput capacity and the full completion relies on additional electricity supply to be provided by power supplier Endesa.

Although work is under way to provide the additional electricity supply, it has not yet been completed and the project is now slightly delayed, Aim- and TSX-listed Atalaya Mining reported on Thursday.

As a result, the company has reviewed its existing production guidance and now expects 10.6-million tonnes of ore to be processed in 2019 with copper produced expected to be in the range of 44 000 t to 45 000 t, compared with the 45 000 t to 46 500 t previously guided.

Atalaya stated that it remained confident that the expansion project would reach nameplate capacity by the end of 2019 with production in 2020 expected to be in the range of 55 000 t to 58 000 t.

In the third quarter, the miner produced 10 568 t of copper, which was in line with expectations, but slightly below the second quarter production, owing to lower recovery levels and copper head grade.

An average copper head grade of 0.47% and a recovery rate of 87.38% for the 2.6-million tonnes of ore processed have resulted in copper production being 2.9% lower than in the second quarter.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 0.93s - 140pq - 2rq
Subscribe Now