Atalaya says Proyecto Riotinto slightly delayed
The Proyecto Riotinto mine, in Spain, expects to reach its expanded throughput rate of 15-million tonnes a year by the end of 2019, despite delays to increased electricity supply.
The expansion project reached full mechanical completion on August 19 and has started ramping up. However, the increase in throughput capacity and the full completion relies on additional electricity supply to be provided by power supplier Endesa.
Although work is under way to provide the additional electricity supply, it has not yet been completed and the project is now slightly delayed, Aim- and TSX-listed Atalaya Mining reported on Thursday.
As a result, the company has reviewed its existing production guidance and now expects 10.6-million tonnes of ore to be processed in 2019 with copper produced expected to be in the range of 44 000 t to 45 000 t, compared with the 45 000 t to 46 500 t previously guided.
Atalaya stated that it remained confident that the expansion project would reach nameplate capacity by the end of 2019 with production in 2020 expected to be in the range of 55 000 t to 58 000 t.
In the third quarter, the miner produced 10 568 t of copper, which was in line with expectations, but slightly below the second quarter production, owing to lower recovery levels and copper head grade.
An average copper head grade of 0.47% and a recovery rate of 87.38% for the 2.6-million tonnes of ore processed have resulted in copper production being 2.9% lower than in the second quarter.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation