https://www.engineeringnews.co.za

Alstom admits boiler protection system tests were not ‘fully satisfactory’

Alstom admits boiler protection system tests were not ‘fully satisfactory’

Photo by Duane Daws

9th July 2013

By: Terence Creamer

Creamer Media Editor

  

Font size: - +

French energy solutions group Alstom acknowledged on Tuesday that tests performed on the boiler protection system (BPS), which forms part of the control and instrumentation (C&I) solution to be installed at the Medupi power station, had not been “fully satisfactory”.

However, in a statement released a day after Eskom announced that the start of the first Medupi unit, Unit 6, had been delayed until the second half of 2014, from the end of 2013, Alstom said it remained confident of delivering its commitments for Medupi “in line with agreed timeframes”.

It described the BPS as a “complex system”, and the requested Medupi configuration as “demanding”.

“No other coal plant has ever been built on this scale. Alstom’s engineers and technicians are committed to resolving all the pending issues with utmost speed,” the company said.

It also argued that the delays could not be attributed to a single contractor, noting that several other contractors were also facing technical problems at Medupi.

“The project has been through critical development phases in recent months, with part of the delivery being delayed due to continued and lengthy labour strikes on site.”

Earlier Eskom confirmed the second half of 2014 as the new, "realistic" deadline for synchronising Medupi's first unit to the grid.

The announcement following an independent assessment and fresh delays to the C&I contract.

Eskom also confirmed that the cost of the project had increased from R91.2-billion to R105-billion, excluding interest during construction.

CEO Brian Dames said that a commercial strategy would be put in place in an effort to recover the additional costs from contractors that failed to deliver. However, he warned that such a recovery process would take time to conclude.

Eskom was also engaging with alternative C&I suppliers, particularly those that had supplied solutions for other power stations within the utility’s fleet.

Alstom said its involvement in the construction of the Medupi and Kusile power stations was a source of great pride for the company and represented a significant portion of Alstom Thermal Power’s South African operations, which included servicing 12 of Eskom's 13 power stations.

Besides the C&I contract, the group is supplying 12 turbine islands across the Medupi and Kusile projects.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 0.842s - 144pq - 4rq
Subscribe Now