Name of the project and location
Afam VI combined-cycle power plant project, Nigeria.

Project description
The project involves the installation of a 600-MW ¬to 700-MW combined-cycle gas turbine-driven power plant at Afam near Port Harcourt, Nigeria. The plant, Afam VI, is required to provide power to the Nigeria national power grid.

Value
Not stated.

Duration
The plant is expected to come on line in April 2007.

Breakdown of main contracts
The supply and site installation of a combined-cycle power plant comprising three or four major identical gas turbine generating sets, their related steam turbine generating equipment and condensing systems, having an aggregate capacity in the range 600 MW to 700 MW at site conditions, complete with all the necessary auxiliaries, controls and electric equipment, including HV switch yard.

The complete civil works construction for the plant, including foundations, sound attenuation enclosures, structures, bunds, drains, and preconstruction works, as required.

The commissioning and testing of the power plant and ancillary systems/equipment.

The operation and maintenance training for the operator.

The management of all related works and issues, notably the establishment of beneficial relationships with local host community.

Client
Shell Petroleum Development Company.

Latest developments
Alstom has won contracts worth over €200-million for the supply of equipment and services for the project. The company will supply three 167-MW-GT13E2 gas turbines. In addition, Alstom will provide long-term operation support and maintenance services for the gas turbines and generators. It will also provide initial technical support to help set up a service organisation at the site.

Participants
Alstom, for the supply of equipment and services.

Daewoo E&C is in charge of the engineering, procurement and construction contract.

On budget and on time?
Not stated.

Contact details for project information
Shell Petroleum Development Company, tel +234 84 429999.
 

Edited by Terence Creamer
Creamer Media Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.054 0.83s - 145pq - 2rq
Subscribe Now