https://www.engineeringnews.co.za

Adventures on the interconnected electricity system

14th September 2018

By: Terry Mackenzie-hoy

     

Font size: - +

In my last column on the Eskom interconnected power system, I explained that I worked for the electricity utility as the senior engineer for operations in the Eastern Cape for just under two years. The backbone of the national grid was the 400 kV powerline system and the 220 kV powerline system, which formed the main transmission system.

The 400 kV and 220 kV powerline systems fed, through transformers, into the 132 kV distribution systems. The whole power system, including distribution, was known as the interconnected power system. Each region – I think there were seven of them – had a 132 kV distribution system. My region, the Eastern Cape, extended from Colesberg to the Transkei border and then south to about 50 km south of Port Elizabeth. Eastern Cape Control reported to me and all I had to do was to make decisions on how to operate the Eskom Eastern Cape region system so as to keep outages to a minimum. I reported to the regional manager through the chief engineer for operations and had a reporting function to National Control, which was on the alert for operating errors in our system.

Here is one adventure. During an infrared inspection of the Pembroke substation, the inspection team noted that the connection to one of the structure-mounted voltage transformers seemed to be very hot. The voltage transformer was on the ‘outboard’ side of the 220 kV Poseidon–Pembroke line.

Replacing the voltage transformer would be difficult, so I asked the live line team to try to see if they could tighten the connections, working on the line live, with special equipment. This had to be done during a period of low load, early on a Sunday morning, since, if something went wrong and the 220 kV line tripped, we would have to try running the whole of East London and surrounding areas on the Port Rex gas turbines – which only supplied 60 MW. The Sunday load of East London and surrounding areas was about 80 MW. This was not enough, so I briefed the Buffalo power station, in East London, to fire up and provide a spinning reserve of 40 MW. We ran through this. Then the live line team did its stuff but the connections remained hot. Not as hot as before, but nonetheless hot. So the voltage transformer would have to be replaced, which we scheduled for the following weekend. We started the gas turbines and picked up the East London and surrounding areas load and opened the 220 kV line infeed from Poseidon. The voltage transformer was replaced. All very good. It was 04:00 when the line links were closed and we waited for the main Poseidon–Pembroke 220 kV circuit breaker to close. The circuit breaker is a four-pole structure of some size, mounted on long insulators. As I stood outside the Pembroke control room, I briefly noticed dancing sparks on the circuit breaker insulators. A moment later, the circuit breaker exploded in a beautiful firework of sparks, flames and burning debris.

I rushed into the control room. Andre, the senior operator on duty, knew what had happened. Clearly, we could not replace the circuit breaker any time soon. Fortunately, there was an option: we could close the parallel bypass circuit breaker. Andre and I sat on the floor, discussing options. He was not in favour of closing the bypass circuit breaker. He thought the circuit breaker which blew up was overstressed by the synchronising voltage. He suggested a clever plan that would involve a ten-minute outage to pick up the East London and surrounding areas load, after which we could close the bypass circuit breaker and switch off the turbines and power station. It worked. When I got home at 06:00 my wife sniffed me for alcohol and, detecting none, asked suspiciously where I had been.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.068 0.126s - 139pq - 2rq
Subscribe Now