https://www.engineeringnews.co.za

Abujar gold project, Côte d’Ivoire

28th May 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Abujar gold project.

Location
Côte d’Ivoire.

Project Owner/s
Exploration and mining company Tietto Minerals.

Project Description
The project has probable mineral reserves of 15.7-million tonnes run-of-mine at 1.7 g/t of gold for 860 000 oz.

A prefeasibility study (PFS) on the proposed 3.02-million-ounce project has shown it to be a robust, long-life operation, based on the openpit mine development.

The Abujar AG openpit PFS forecasts production of 182 000 oz of gold in years 1 to 3, and more than 168 000 oz/y over the first six years of the project.

The project has a life-of-mine (LoM) of ten years. LoM recoveries are estimated at 1.08-million ounces of gold.

The expanded project, comprising the Abujar AG openpit PFS, APG openpit scoping study and AG underground study envisages average production of 182 000 oz/y of gold in years 1 to 3, and 168 000 oz/y in years 1 to 6.

The project has an LoM of 12 years. LoM recoveries are estimated at 1.44-million ounces of gold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The Abujar AG openpit PFS has a net present value, at a 5% discount rate, of $363-million and an internal rate of return of 53%, with a payback of 2.4 years on initial capital.

The Abujar AG openpit PFS, APG openpit scoping study and AG underground study forecasts a pretax net present value, at a 5% discount rate, of $432-million and an internal rate of return of 54%, with a payback of 2.4 years on initial capital.

Capital Expenditure
$230-million, including preproduction mining and contingency.

Planned Start/End Date
Not stated.

Latest Developments
The Abujar AG openpit PFS will be used as the basis for a definitive feasibility study, expected in the third quarter of 2021, and build on the value drivers that have been identified.

A PFS will be undertake to assess heap-leach potential at APG to add to gold production at Abujar.

Meanwhile, Tietto has secured all mining and environmental approvals for Abujar; negotiations with the Côte d’Ivoire government onthe Abujar Mining Conventionare under way, with ratification expected in the second quarter of 2021.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Tietto Minerals, tel +61 8 9331 6710 or email admin@tietto.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.858s - 147pq - 2rq
Subscribe Now