Yanfolila ramp-up on track - Hummingbird
JOHANNESBURG (miningweekly.com) - Since first gold was poured at Aim-listed Hummingbird Resources' Yanfolila gold mine, in Mali, on December 19, the mine has steadily been ramping up towards full production, in line with the company's planned schedule.
"I am pleased that activity on site is steadily progressing as per the ramp-up schedule and we are on track to achieve nameplate capacity from the plant by the end of the first quarter," Hummingbird CEO Dan Betts commented in a statement published on Friday.
He further highlighted the technical performance of the mine's plant, with recoveries already at over 95% and a "solid performance" of the milling circuit.
This, he enthused, stands the company in good stead as it continues to ramp up the performance of the operation.
A total 10 737 oz of gold has been recovered, to date, of which 5 483 oz has been shipped to refiners.
The company noted that the plant had, initially, been processing ore from the lower-grade stockpiles, in order to ensure plant performance and gold recovery were satisfactory before increasing the head grade.
Now that the plant is running close to nameplate capacity and recoveries remain consistently high, higher-grade ore is increasingly being introduced to the plant.
Meanwhile, the 2018 exploration programme at Yanfolila has also started, with the focus on the conversion of indicated and inferred resources to mineable reserves.
Yanfolila has over one-million ounces of resources outside the mine plan, which Hummingbird is targeting for conversion into reserves. It plans to spend between $8-million and $10-million on exploration this year, but not more than 15% of Hummingbird's operating cash flows from Yanfolila.
The company aims to pursue an aggressive exploration strategy to extend the mine life, which will be controlled by strict financial discipline.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation