The construction of the second ball mill at Hummingbird Resources’ Yanfolila gold mine, in Mali, has been completed ahead of time and within budget.

Commissioning is set to begin “imminently” and it is expected that ore will be introduced to the mill this month – a month earlier than previously expected. 

When fully operational, the ball mill will increase throughput capacity from one-million tonnes to 1.2-million tonnes a year.

Hummingbird CEO Dan Betts on Monday commented that the commissioning of the ball mill, “is testament to the hard work of our staff and contractors who have worked extremely well together to deliver this project so successfully”.  

He added that Hummingbird looked forward to the positive benefits the second ball mill would bring, specifically the increased plant throughput capacity and the resultant economies of scale as the mine transitioned to a higher gold production rate.  

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 1.217s - 140pq - 2rq
Subscribe Now