Name and Location
Wedza Phase 5,5 brownfield expansion, Mimosa platinum mine, Zimbabwe.

Project Description
The project involves the expansion of the Mimosa platinum mine to 200 000 t/m run-of-mine (Rom).

The expansion project, known as Wedza Phase 5,5, follows earlier successful expansion projects at Mimosa.

The latest expansion is the result of the increase in Rom and the subsequent need to increase the crushing and screening, floating and tailings capacity, in line with the overall strategy of Mimosa Mining.

Value
Total capital cost of the expansion is estimated at $15-million and will be funded from retained cash flows.

Duration
Design work on the project started in April 2008. The hot commissioning of the plant was completed in May 2009, with full production achieved.

Client
Mimosa Mining, whose key shareholders are Aquarius Platinum and Impala Platinum.

Latest Developments
A detailed resource evaluation for the Wedza VI expansion is under way, prior to seeking board approval for a final feasibility study.

Key Contracts and Suppliers
DRA (main engineering, procurement and construction management contractor).

On Budget and on Time?
The project will yield savings against budget and was completed one day earlier than planned.

Contact Details for Project Information
Mimosa Mining, Herbert Mashanyare, tel +263 4 708040.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.041 0.45s - 127pq - 2rq
Subscribe Now