Vele colliery expansion project, South Africa

8th August 2014

  

Font size: - +

Name and Location
Vele colliery expansion project, Limpopo, South Africa.

Client
Coal of Africa Limited (CoAL).

Project Description
As at September 28, 2012, Vele had Joint Ore Reserves Committee-compliant resources of:
• 795.7-million gross tonnes in situ and 672.9-million mineable tonnes in situ of shallow-dip coal;
• 362.5-million tonnes, including 42.4-million tonnes of proven reserves and 325.6-million tonnes of probable reserves; and
• 42.4-million tonnes of run-of-mine (RoM) from the central and northern pits over a 16-year period, producing 16.5-million tonnes of saleable product.

The mine is currently configured as an opencast mine, but underground mining is a possibility in the future, owing to the significant resource.

A modular coal treatment plant has been established during the first phase of the project.

CoAL is modifying and expanding its Vele colliery beneficiation plant, which will enable CoAL to optimally produce semisoft coking coal, thermal coal and sized coal simultaneously at an expected processing capacity of 2.7-million tonnes a year of RoM. The planned three-month front-end engineering and design (Feed) process will enable CoAL to arrive at a class 1 engineering, procurement and construction estimate.

The scope of work for the Feed contract includes:
• identifying and improving sections of the existing plant to ensure a 500 t/h throughput capacity;
• a stockpile management philosophy and associated design;
• an RoM handling, crushing and screening section;
• a destoning wash plant;
• a sized-coal screening plant;
• a classifier in the fines beneficiation circuit;
• a froth flotation plant for the beneficiation of the ultrafines; and
• products and discard stockpiling and load-out facilities.

Value
The total capital expenditure to complete plant modification is estimated at R450-million and includes the necessary mine development and production ramp-up.

Duration
The expansion project will be completed by the end of 2015, with production ramp-up in early 2016.

Latest Developments
With the front-end engineering and design (Feed) process, legislative compliance work and technical review for the beneficiation plant modification project at the Vele colliery all expected to be completed by the third quarter of this year, CoAL is on track to start construction of the plant at year-end.

Mineral processing and associated infrastructure solutions company Sedgman South Africa was appointed to undertake the Feed process in February, while the technical review is being completed by Snowden.

Further, CoAL expected to convert current discussions with potential customers into formal offtake agreements during the second half of this year.

Meanwhile, the miner is confident of securing an amended environmental authorisation from the Department of Environmental Affairs during the third quarter.

Extensive work on the application to amend the colliery's integrated water-use licence to include the plant modifications was undertaken during the June quarter, with the application expected to be submitted this month.

Key Contracts and Suppliers
Sedgman South Africa (Feed).

On Budget and on Time?
Not started.

Contact Details for Project Information
CoAL head of engineering, Nico Pretorius, email nico.pretorius@coalofafrica.com; or investor relations and business development manager Celeste Harris, email celeste.harris@coalofafrica.com

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 
Kriel Occupational Health Centre
Kriel Occupational Health Centre

Occupational health services, mobile clinics, wellness campaigns, aviation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.064 1.07s - 147pq - 2rq
Subscribe Now