Upper Lillooet hydro project, Canada
Name and Location
Upper Lillooet hydro project, British Colombia, Canada.
Client
Creek Power, a joint venture between Innergex Renewable Energy (66.6%) and Ledcor Power Group (33%).
Project Description
The project includes two run-of-river, clean energy generation facilities – the 81.4 MW Upper Lillooet river hydroelectric facility and the 25.3 MW Boulder (Pebble) Creek hydroelectric facility – located in the Pemberton Valley.
Each hydroelectric facility will divert partial flows from the river or creek through an intake structure directly into a tunnel and/or penstock to the turbine(s) and generating equipment, located in each powerhouse. The water will then be returned to each river/creek.
Electricity generated by the hydroelectric facilities will be transmitted by a single 230 kV transmission line, which will be built to connect the hydroelectric facilities to the BC Hydro transmission system. The transmission line route does not pass through Pemberton.
The project initially included three run-of-river facilities – the Upper Lillooet river, Boulder Creek and North Creek – with a combined capacity of 121 MW. In March 2013, Creek Power announced changes to the configuration of the project, which included the proposed cancellation of the North Creek facility.
Value
Not stated.
Duration
Construction of the 25.3 MW Boulder Creek facility was expected to start in 2013 and the project is expected to reach commercial operation in 2015. Construction of the 81.4 MW Upper Lillooet river facility is expected to start in 2013, with the project expected to reach commercial operation in 2016.
Latest Developments
Discussions are ongoing with BC Hydro to obtain its consent to amend the environmental protection assessments to increase the installed capacity of the Boulder Creek and Upper Lillooet river hydroelectric facilities and to cancel the North Creek hydroelectric facility.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Creek Power, email info@upperlillooethydro.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation