Tschudi copper 44% complete, on track for Q2 2015 production

19th May 2014

By: Leandi Kolver

Creamer Media Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Aim-listed Weatherly International on Monday announced that, as at end April, its Tschudi copper project, in Namibia was 44% complete and on schedule to produce its first copper in the second quarter of 2015.

The company also stated that Tschudi’s financial model had been updated by advisory company Minxcon, resulting in an after tax net present value of $133-million, while the life-of-mine cash cost for the project had been calculated at $4 226/t of copper.

The breakeven price had been calculated at $4 675/t of copper.

According to Minxcon “under the consensus economics forecast for copper prices, the project is robust with an internal rate of return of 89%”.

“It is good to see that 15 months on there has been a reduction in the project's operating costs and an increase in [its] overall value,” Weatherly CEO Rod Webster commented.

Meanwhile, Weatherly also reported that – as a result of ongoing efforts to improve productivity and changes to its underground mining operations, which included moving all mining activity in-house, improving the company’s fleet and moving away from pillar mining towards primary mining – production for the quarter was progressing at an annualised rate of 6 000 t of contained copper.

Costs for the quarter so far were also well below those reported for the previous quarter.

Weatherly operated the Matchless and Otjihase underground copper mines in Namibia.

Edited by Tracy Klückow
Creamer Media Contributing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.079 1.03s - 140pq - 2rq
Subscribe Now