Toliara DFS targeted for Dec completion

4th September 2019

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – The definitive feasibility study for the Toliara mineral sands project, in Madagascar, is due for completion by December this year, ASX-listed Base Resources said on Wednesday.

Speaking at the Paydirt Africa Downunder conference, in Perth, Base MD Tim Carstens noted that a final investment decision on the project was expected by early to mid-2020, allowing for first production in 2022.

A previously completed prefeasibility study (PFS) into Toliara estimated that the project could produce some 37.1-million tonnes of heavy mineral concentrate over a life-of-mine of 33 years.

The PFS envisaged a two-stage development option, with the Stage 1 operation estimated to cost $439-million to develop a 13-million-tonne-a-year operation, while the Stage 2 operation would expand production to 19-million tonnes a year, for an additional cost of $67-million.

Toliara is expected to deliver annual average production of 806 000 t of ilmenite, 54 000 t/y of zircon and 8 000 t/y of rutile.

“We are currently establishing early capability and capacity building programmes at Toliara, advancing land acquisition and initiating the debt funding process,” Carstens said on Wednesday.

“This is a truly world-class mineral sands development project with a long mine life.”


 


 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.049 0.989s - 140pq - 2rq
Subscribe Now