Name and Location
Thunderbox gold project, Australia.

Client
Saracen Mineral Holdings.

Project Description
A feasibility study on Stage 1 of the Thunderbox operations has been completed, with the study showing robust economics over an initial 4.5-year mine life. It further envisages the development of a large openpit on the Thunderbox deposit, delivering 597 000 oz.

The start of mining will coincide with the completion of the Whirling Dervish openpit, allowing for a seamless integration between operations.

Several opportunities exist to extend the project life beyond Stage 1, including a bulk underground mine at Thunderbox and satellite openpit opportunities.

Stages 2 and 3 could potentially extend production to more than one-million ounces over an eight-year mine life at an average production rate of 126 000 oz/y.

Net Present Value/Internal Rate of Return
Stage 1 has a net present value, at an 8% discount rate, of A$120-million and an internal rate of return of 59%.

Value
A$65-million.

Duration
First gold from Stage 1 is planned for July 2016.

Latest Developments
Saracen expects first gold production from its Thunderbox gold mine in the June 2016 quarter, three months ahead of schedule.

The project is expected to be commissioned in the March quarter, as significant progress has been made in mining, plant refurbishment and infrastructure.

Mining started in early July, also ahead of schedule and, to date, material movement is about 7% ahead of budget.

MD Raleigh Finlayson has said excellent progress made at Thunderbox has placed Saracen in an outstanding position.

Meanwhile, Saracen has also taken advantage of the recent increase in the Australian gold price, hedging a further 40 000 oz at an average price of A$1 600/oz to further underpin the first year of production at Thunderbox.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The project is ahead of schedule.

Contact Details for Project Information
Saracen Mineral Holdings, tel +61 8 6229 9100 or fax +61 8 6229 9199.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.764s - 146pq - 2rq
Subscribe Now