Thunderbird mineral sands project, Australia – update
Name of the Project
Thunderbird mineral sands project.
Location
Kimberley region, northern Western Australia.
Project Owner/s
Kimberley Mineral Sands (KMS), a 50:50 joint venture between Sheffield Resources and YGH Australia Investment.
Project Description
A bankable feasibility (BFS) has been completed on a simplified process flowsheet for the project, which has resulted in lower capital costs and improved margins for a significant improvement in project economics.
The 2022 BFS has removed the ilmenite processing circuit, which included the low-temperature roaster circuit and ilmenite magnetic separation circuit included in the 2019 bankable feasibility study update.
The BFS flowsheet is expected to produce a nonmagnetic concentrate product containing zircon and rutile, an ilmenite-rich magnetic concentrate and a paramagnetic concentrate.
Thunderbird will be developed in two stages.
Stage 1 and 2 of operations is expected to produce 1.4-million tonnes a year of zircon and ilmenite concentrates over an estimated 36-year life-of-mine (LoM).
The initial Stage 1 mining and processing feed rate is forecast at 1 085 dry tonnes an hour at the wet concentrate plant, with Stage 2 doubling the wet concentrate feed rate to 2 170 t/h during Year 5 of operations.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The BFS delivers a prefinance, after-tax net present value, at an 8% discount rate, of A$1.28-billion and internal rate of return of 27.5% over the LoM.
Capital Expenditure
Stage 1 is estimated at $361-million, including contingency. Total funding requirements for Stage 1 are estimated at A$484-million.
Planned Start/End Date
First production is targeted for the first quarter of 2024.
Latest Developments
Western Australia deputy premier Roger Cook has ratified a A$160-million Northern Australian Infrastructure Facility (NAIF) loan facility for the development of the Thunderbird mineral sands project.
In conjunction with third-party project financing being sourced by Kimberley Mineral Sands, the execution of the NAIF loan documentation is one of the remaining steps to enable KMS to achieve financial close and use the loan facilities, which is expected over the coming months.
Key Contracts, Suppliers and Consultants
GR Engineering Services (engineering, procurement and construction – process facilities).
Contact Details for Project Information
Sheffield Resources, tel +61 8 6555 8777 or email info@sheffieldresources.com.au.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation