https://www.engineeringnews.co.za

Thor envisions Nigeria gold mine construction to start in Q2

5th February 2019

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

Canadian junior Thor Exploration’s definitive feasibility study (DFS) at its Segolila gold project, in Nigeria, envisions a construction start date in the second quarter of the year and an 18-month construction period, for an initial five-year mine life.

The company is proceeding with engineering, procurement and construction documentation with its preferred contractor, Norinco International, which also assisted with the feasibility study.

Further, Thor announced on Monday  the completion of an independent preliminary economic assessment (PEA), undertaken by Roscoe Postle Association, for a proposed supplemental underground project at Segolila.

The DFS comprises an openpit mine and includes construction of a 625 000 t/y processing plant, which will consist of a conventional crushing circuit, two-stage grinding, gravity, carbon-in-leach, elution, eletrowinning and smelting to produce gold ore.

The DFS estimates a post-tax internal rate of return of 50% on the Segolila project, with pre-production capital of $87-million required, while the PEA estimates further development capital of $13-million for the underground project.

It is also estimated by the DFS that the project can produce an average 80 000 oz/y at an all-in sustaining cost of $662/oz. The probable mineral reserves for Segolila stand at three-million tonnes grading 4.2 g/t gold, containing 405 600 oz at 0.77 g/t cut-off.

Meanwhile, the underground project considers an initial three-year underground operation, which can be brought on during the openpit mine life to supplement the pit ore with high grade underground production. The deposit remains open below the resources that are considered in the underground project.

Edited by Mariaan Webb
Creamer Media Contract Publishing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.414s - 140pq - 2rq
Subscribe Now