Name and Location
Thang Long thermal power plant project, Quang Ninh province, Vietnam.

Client
Thang Long Power Plant JSC.

Project Description
The project involves the construction of two 300 MW circulating fluidised boilers (CFB) for the coal-fired power plant, in the northern province of Quảng Ninh, and will cover more than 124 ha.

The boilers will burn anthracite in the cleanest and efficient conditions, helping to reach the regulatory limits for nitrogen oxide and sulphur oxides without the need for additional back-end flue gas treatment such as selective catalytic reduction and flue gas desulphurisation.

The project comprises the main plant, a coal storage facility and supporting infrastructure. Once operational, the plant is expected to contribute an estimated 4 185 GWh/y to the national grid.

Value
The project is estimated at more than $1-billion.

Duration
Construction on the power plant started in October 2014 and is expected to take 45 months to complete.

Latest Developments
Alstom has been awarded a contract to design and supply two 300 MW circulating fluidised-bed boilers for the power plant. Once these are completed, they will be the largest CFB boilers in Vietnam.

Key Contracts and Suppliers
Wuhan Kaidi Electric Power Engineering (construction).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Wuhan Kaidi Electric Power Engineering tel +86 27 67869001 or fax +86 27 67869010.
Alstom, Christopher English, tel +33 1 41 49 26 85 or email christopher.english@alstom.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.782s - 145pq - 2rq
Subscribe Now