Texas LNG project, US
Name of the Project
Texas LNG project.
Location
The proposed project will built on the Brownsville Ship Channel in Cameron County, Texas, in the US.
Client
Texas LNG Brownsville.
Project Description
The project entails the construction of a proposed two-train, four-million-tonne-a-year liquefied natural gas (LNG) export facility.
The project will be built in two phases, each with a capacity of two-million tonnes a year. The project includes:
- a gas gate station and interconnect facility;
- a pretreatment facility;
- an open art turbo-expander for pentane plus heavy carbon removal;
- a liquefaction plant consisting of two liquefaction trains and ancillary support facilities;
- two 210 000 m3 aboveground full containment LNG storage tanks with cryogenic pipeline connections to the liquefaction plant and berthing dock;
- an LNG carrier berthing dock capable of receiving LNG carriers between 130 000 m3 and 180 000 m3 in capacity;
- a permanent material offloading facility to allow waterborne deliveries of equipment and materials during construction and mooring of tug boats while an LNG carrier is at the berth; a thermal oxidiser, a warm wet flare, a cold dry flare, a spare flare, an acid gas flare, and a marine flare; and
- administration, control, maintenance, and warehouse buildings and related parking lots; electrical transmission line and substation, water pipeline, septic system, and stormwater facilities/outfalls.
Natural gas will be delivered to the Texas LNG project site through a nonjurisdictional intrastate, 30-inch-diameter natural gas pipeline that will be built, owned and operated by a third party, separate from Texas LNG.
Potential Job Creation
Not stated.
Value
Not stated.
Duration
Commercial operation is expected in 2023/24.
Latest Developments
The remaining milestones in the permitting process, include the receipt of the final environ-mental-impact statement by March 15, 2019, and the June 13, 2019, Federal Authorization Decision Deadline.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Texas LNG Brownsville, email info@txlng.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation