T3 copper/silver project, Botswana

1st September 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
T3 copper/silver project.

Location
The project is located in the Kalahari Copperbelt, in Botswana.

Client
The project is a joint venture (JV) between Metal Tiger and MOD Resources.

Project Description
The T3 project has a maiden mineral resource comprising 28.36-million tonnes, containing about 350 200 t of copper and 14.27-million ounces of silver. This includes a high-grade resource using a 1.5% copper cutoff grade, which consists of 8.48-million tonnes grading 2.16% copper and 30.6 g/t silver, containing an estimated 183 000 t of copper and 8.34-million ounces of silver. About 64% of the total T3 resource (0.5% copper cutoff) is in the indicated resource category and 88% of the total scoping study production target is in the indicated resource category.

A scoping study on the project envisages a two-million-tonne-a-year operation, producing about 21 800 t/y of copper and 665 000 oz/y of silver over a ten-year mine life.

Jobs to be Created
Not stated.

Net Present Value/Internal Rate of Return
The project is expected to have a net present value, at a 10% discount rate, of $297-million and an internal rate of return of about 42%, with a payback of about two years.

Value
The base case model on the project will require a capital investment of $135-million.

Duration
The project is expected to enter production in the fourth quarter, subject to all regulatory approvals being received.

Latest Developments
MOD Resources has reported a 16% increase in the contained copper at the T3 project, which is now estimated to host a total mineral resource of 36-million tonnes, at 1.14% copper and 12.8 g/t silver for an estimated 409 000 t of copper and 14.8-million ounces of silver.

The resource upgrade follows drilling work completed in the March quarter of this year.

As a result of the increased resource estimate, MOD’s feasibility team is rethinking the planned mining schedule and processing rate to be used in the prefeasibility study.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
MOD Resources, tel +61 8 9322 8233, fax +61 8 9322 8077 or email administrator@modresources.com.au.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.082 1.143s - 239pq - 2rq
Subscribe Now