Sumatra's Tembang gold project faces possible delay

17th September 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Metals developer Sumatra Copper & Gold has flagged a possible delay to the start of its Tembang mine, in Indonesia, as it implements a revised mine plan.

Earlier this year, Sumatra initiated a series of optimisation studies to de-risk the Tembang project both in terms of the volatile gold price and project economics. The company took the decision to revise the mine strategy based on mining the Buloh and Asmar deposits during the Stage 1 development.

The company also decided to progress the Belinau deposit as an underground mine from the outset, rather than starting with an initial pit cutback.

The revised mine plan was expected to substantially improve the cash flow over the first two years of the project life, and to lower cash costs, which should translate into improved project economics.

Sumatra said on Tuesday that the optimised mine plan and an updated mineral resource would be completed in the fourth quarter, allowing the finalisation and draw-down of the project funding package.

However, Sumatra pointed out that the timeline to production would likely be delayed by the later-than-expected draw-down of the debt funding. The final funding plan would only be confirmed once the updated mine plan had been finalised and reviewed.

As a cautionary measure, Sumatra has slowed project expenditure commitments until a final funding arrangement was in place.

In the meantime, significant progress had already been made with initial construction works on site, and detailed engineering was nearing completion. Long-lead items had also been placed on order, and road access to the site had been completed, while the 300-person accommodation camp was also nearing completion.

The project has a reserve estimate of 5.5-million tonnes, grading 2.3 g/t gold and 31.4 g/t silver for 513 000 oz of gold equivalent.

The Stage 1 operation would produce 400 000 t/y of ore and would have a mine life of around five years.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
The Beneficiation Academy
The Beneficiation Academy

The Beneficiation Academy is a certified training institution that follows all compliance legislation and is accredited with various Sector...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.062 0.097s - 140pq - 2rq
Subscribe Now