Stage 4 until weekend as even more units break down at Kendal, Majuba
Eskom will be implemented at Stage 4 throughout Thursday and Friday, with only a possibility of lower stages from Saturday morning, Eskom said on Wednesday.
"Eskom teams are working around the clock to return units to service, but in view of the shortage of generation capacity and the need to carry out unplanned maintenance to return units to service, we unfortunately have to implement load shedding as a last resort," Eskom spokesperson Sikonathi Mantshantsha said in a statement.
The extension of the Stage 4 load shedding is due to further breakdowns of a generation unit each at Kendal and Majuba this morning due to boiler tube leaks.
Eskom also saw breakdowns during the past few days of three generating units each at Kendal and Tutuka power stations, as well as the delayed return of a unit at Camden Power Station.
Planned maintenance is ongoing at Arnot, Kriel, Matimba, Matla and Camden power stations due to "known risks" after extensive use in the last bout of load shedding. Currently 5 209MW on planned maintenance, while another 16 669 MW of capacity is unavailable due to breakdowns.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation