Name of the Project
Sonora lithium project.

Location
Sonora state, Mexico.

Client
Bacanora Minerals.

Project Description
A feasibility study on the project has confirmed the positive economics and favourable operating costs of 35 000 t/y of battery-grade lithium carbonate (Li2CO3).

The project has measured and indicated mineral resources estimated at five-million tonnes comprising 1.9-million tonnes of measured resources and 3.1-million tonnes of indicated resources of lithium carbonate equivalent (LCE) and an additional inferred mineral resource of 3.7-million tonnes of LCE.

The feasibility study envisages an openpit operation using continuous miners to mine the ore zones and a truck-and-shovel fleet to remove the waste material. An estimated 37.1-million tonnes of ore will be mined over the planned 19-year mine life, with a lithium grade of 4 151 parts per million and an average stripping ratio of about 3.4:1 over the life-of-mine.

The process plant has been designed to initially process 1.1-million tonnes a year of ore during Stage 1 of the project, subsequently increasing to an estimated 2.2-million tonnes a year at Stage 2, producing 17 500 t/y and 35 000 t/y of Li2CO3 respectively.

The plant design also includes a circuit to produce up to 30 000 t/y of potassium sulphate and/or sulphate of potash product through a series of evaporation and precipitation stages.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The feasibility study estimates a pretax net present value, at an 8% discount rate, of $1.25-billion and an internal rate of return of 26.1%, with a simple payback Stage 1 of four years.

Value
Stage 1 of the project is expected to cost about $419.62-million and Stage 2 $380.26-million.

Duration
Construction is expected to start in the first half of 2018, with production targeted for the first quarter of 2020.

Latest Developments
Bacanora Lithium, which previously announced a funding package for the development of the Sonara project, has terminated its proposed $100-million placing, citing “difficult market conditions”.

Instead, the company will focus on completing the front-end engineering design while continuing discussions with several additional parties to secure the remainder of the construction funding.

Bacanora still needs about 48% of the $460-million that is required for Stage 1 production. To date, it has announced equity and debt funding commitments totalling $240-million, including a $150-million senior debt facility with RK Mine Finance and conditional strategic investments from the State General Reserve Fund of Oman, the sovereign wealth fund of the Sultanate of Oman, and from Bacanora's offtake partner, Hanwa, for a combined total of $90-million.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Bacanora Minerals, tel +1 403 237 6122, fax +1 403 237 6144 or email info@bacanoraminerals.com.

 

 

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Aluminium Federation of South Africa
Aluminium Federation of South Africa

The Aluminium Federation of South Africa (AFSA), is the voice of the South African aluminium industry.

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 0.111s - 127pq - 2rq
Subscribe Now