Songo–Matambo transmission line project, Mozambique
Name of the Project
Songo–Matambo transmission line project.
Location
Cahora Bassa and Changara districts, Mozambique.
Project Owner/s
Electricidade de Moçambique (EDM).
Project Description
The project comprises the construction of a 118 km 400 kV high-voltage single-circuit transmission line from Songo to Matambo. The line is planned to pass through the site where the future Cataxa substation will be built to integrate the envisaged Mphanda Nkuwa hydropower plant. It will use self-supporting steel mesh overhead towers carrying a horizontal conductor configuration with an energy transport capacity of 2 300 MW.
The project includes the expansion of the Songo substation to extend the 220 kV busbar, the installation of a new 600 MVA 220/220 kV phase shift transformer to regulate grid flows and a 3 200 MVA 220/400 (300) kV step-up transformer. The project will also result in the current 3 × 200 MVA 220/400 (300) kV transformer being refurbished.
Extensive work will also be carried out at the Matambo substation, which will be expanded. A new 400 kV feed supply to the new 400 kV Matambo extension will be built to integrate the 400 kV line from Songo.
Potential Job Creation
Not stated.
Capital Expenditure
$96.57-million.
Planned Start/End Date
The project is expected to be completed in 2028.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
EDM, tel +258 21 322071.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation