Robex progresses Kiniero toward first gold pour in the fourth quarter

Kiniero overview showing completed mill foundations and CIL tanks

Kiniero overview showing completed mill foundations and CIL tanks

Photo by Robex Resources Inc.

3rd April 2025

By: Sabrina Jardim

Senior Online Writer

     

Font size: - +

West African gold producer and developer Robex Resources says it is on track to deliver first gold at its Kiniero gold project, in Guinea, in the fourth quarter of this calendar year.

TSX-V-listed Robex says it expects to produce 155 000 oz of gold at Kiniero in 2026.

"Kiniero continues to progress to schedule and budget and we remain on track to achieve first gold pour at the project in fourth quarter of calendar year 2025. It is exciting to see this project taking shape and our teams working together in a safe and responsible manner to achieve this deadline.

“It continues to be incredibly busy on site with many key aspects of the project now coming into play. We are keeping a close eye on our targets to ensure they remain achievable as we work towards first gold by the end of the year,” says Robex MD and CEO Matthew Wilcox.

Robex says construction continues to track well against the schedule, with the semiautogenous grinding and ball mill foundation completed.

The company notes that the primary crusher run-of-mine (RoM) wall is now complete and backfilling of the RoM pad has begun.

Additionally, it notes that lining of the tailings storage facility began in March.

Robex also notes that power station concrete works began, with excavation and blinding of the engine bases.

The company says next steps include awarding major contracts including mill installation, mining, haulage and drill and blast; commencing design of the solar farm; mobilisation of structural, mechanical and piping contractor in the second quarter of the current calendar year; and mobilisation of a mining contractor in the third quarter of the calendar year.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
The Beneficiation Academy
The Beneficiation Academy

The Beneficiation Academy is a certified training institution that follows all compliance legislation and is accredited with various Sector...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 1.157s - 140pq - 2rq
Subscribe Now