Africa|Building|Business|Construction|Contractor|ELB|Electrical|Energy|Engineering|Health|Installation|Juwi|Manufacturing|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|SECURITY|Services|Siemens|Solar|System|Training|Transformer|Turbines|Waste|Contracting|Equipment|Maintenance|Manufacturing |Solutions|Turbines|Waste|Operations|Transformer
Africa|Building|Business|Construction|Contractor|ELB|Electrical|Energy|Engineering|Health|Installation|Juwi|Manufacturing|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|SECURITY|Services|Siemens|Solar|System|Training|Transformer|Turbines|Waste|Contracting|Equipment|Maintenance|Manufacturing |Solutions|Turbines|Waste|Operations|Transformer
africa|building|business|construction|contractor|elb|electrical|energy|engineering|health|installation|juwi|manufacturing|power|project|projects|renewable-energy|renewable-energy-company|security|services|siemens|solar|system|training|transformer-company|turbines-company|waste-company|contracting|equipment|maintenance|manufacturing-industry-term|solutions|turbines-person|waste|operations|transformer

Renewable Energy Independent Power Producer Procurement Programme – fourth window, South Africa

25th September 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name and Location
Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) – fourth window.

Location
South Africa.

Project Owner/s
Department of Energy (DoE).

Project Description
Twenty-seven REIPPPP project agreements were signed in April 2018.

The preferred bidders include 12 wind farm projects and 12 solar photovoltaic (PV) projects. The list also includes the 100 MW Redstone concentrated solar power (CSP) project, in the Northern Cape, the 5 MW Kruisvallei mini-hydro project, in the Free State, and the 25 MW Ngodwana Energy biomass project, to be fuelled using waste Sappi wood chips, in Mpumalanga.

The wind projects include:

  • Roggeveld Wind Farm (147 MW)
  • Karusa Wind Farm (140 MW)
  • Nxuba Wind Farm (140 MW)
  • Golden Valley Wind Farm (120 MW)
  • Oyster Bay Wind Farm (140 MW)
  • Soetwater Wind Farm (140 MW)
  • Kangnas wind project (140 MW)
  • Perdekraal East Wind Farm (110 MW)
  • Excelsior wind energy facility (32 MW)
  • Wesley-Ciskei Wind Farm (35 MW)
  • Copperton Wind Farm (102 MW)
  • Garob Wind Farm (140 MW).


The solar PV projects include:

  • Sirius Solar PV Project One (75 MW)
  • Droogfontein 2 Solar (86 MW)
  • Dyason’s Klip 1 (75 MW)
  • Dyason’s Klip 2 (75 MW)
  • Konkoonsies II Solar Facility (86 MW)
  • Aggeneys solar project (45 MW)
  • Loeriesfontein Orange project (75 MW)
  • De Wildt solar project (50 MW)
  • Bokamoso solar project (78 MW)
  • Zeerust development (75 MW)
  • Greefspan PV Power Plant Number Two solar park (55 MW)
  • Waterloo solar park (86 MW).


Potential Job Creation
The 27 new projects will potentially create 58 000 new jobs, mostly during construction and mostly in the rural areas of the Northern, Eastern and Western Cape provinces, as well as the North West, Free State and Mpumalanga provinces. There is also potential to create a further 1 500 jobs in the manufacturing sector as a direct spin-off from the projects.

Capital Expenditure
The successful fourth-round bids are valued at an estimated R56-billion.

Planned Start/End Date
Building Energy’s Roggeveld Wind Farm, which is expected to be South Africa’s most efficient wind farm, started construction in April 2018 and is expected to be completed in 2021.

Construction on Enel Green Power’s Nxuba Wind Farm started in February 2019 and is expected to be completed by September 2020.

Construction of Enel Green Power’s Oyster Bay and Garob wind farms is expected to start by the first half of 2019, while Soetwater and Karusa are expected to start construction in the second half of 2019.

All five wind farms are expected to be operational by 2021.

Oyster Bay is expected to be operational in the first half of 2021, while Garob, Soetwater and Karusa are expected to be operational in the second half of 2021.

Mainstream Renewable Energy’s Kangnas Wind Farm started construction in June 2018 and is expected to be complete in late August 2020.

Mainstream Renewable Energy’s Perdekraal East Wind Farm started construction in June 2018 and is expected to be completed in late 2020.

BioTherm Energy’s Excelsior and Golden Valley wind farms started construction in 2018 and are expected to reach commercial operation by the fourth quarter of 2019 and the fourth quarter of 2020 respectively. Construction of the Konkoonsies II and Aggeneys solar PV projects started in 2018 and are expected to reach commercial operation in the third quarter of 2019 and the first quarter of 2020 respectively.

Construction of Innowind’s Wesley-Ciskei Wind Farm is expected to start in December 2019 and production to start in June 2021.

Elawan Energy’s Copperton Wind Farm is expected to come into operation in 2020.

Scatec Solar’s Sirius Solar, as well as Dyason’s Klip 1 and 2 solar PV projects, are expected to enter into operation towards the end of 2019.

juwi started construction on the Droogfontein 2 and Bokamoso solar projects in 2018. Waterloo was expected to start construction in the first half of 2019. In August 2020, juwi announced that the Droogfontein 2 Solar Park, near Kimberley, had reached full grid code compliance and started commercial operations.

Construction of GRS’ Greefspan PV Power Plant Number Two solar park will start in September 2019 and is expected to be completed by November 2020.

Latest Developments
Wind projects:
Nordex South Africa is supplying turbines to the Roggeveld and Nxuba wind farms in the Eastern Cape, as well as the Copperton and Garob wind farms in the Northern Cape, which are all under construction.

Vestas is supplying 70 of its wind turbines to the Karusa and Soetwater wind farms, in the Northern Cape. The massive pieces of equipment are expected to be operational by the second half of 2020.

Concor and Conco Consortium have been appointed as construction contractors for the Kangnas and Perdekraal wind farms, in the Northern Cape, while Siemens Gamesa Renewable Energy will supply and install the wind turbines. The wind turbine sections are being manufactured locally.

The main transformer for the 140 MW Kangnas Wind Farm was energised on September 21, 2020. The 250 MVA transformer was locally manufactured.

Renewable-energy project developer Conco is responsible for the electrical component of the balance of plant works, including the engineering, procurement and construction, as well as the electrical works, for the wind farm.

BioTherm Energy’s Excelsior Wind Farm was connected to South Africa’s load-shedding-prone national grid, with all 13 of its wind turbines having been successfully commissioned in September 2020.

The facility is expected to achieve its commercial operations date in October 2020 and begin generating more than 132 GWh of renewable power each year for the 20-year duration of its power purchase agreement.

Excelsior is connected to the grid through an on-site substation and a dedicated 132 kV power line that is connected to the Vryheid substation, located close to the plant in Swellendam.

Solar projects:
Droogfontein 2 has reached full grid code compliance and has started commercial operations. The 179 ha area, which comprises 260 000 solar panels on a single-axis tracker system, is supplying 75 MW to the national grid.

Bokamoso has started commercial operation has started to generate 177 660 MWh/y of green electricity. More than 450 people from the local beneficiary communities were directly employed on the project during construction, in addition to the employment created through the contracting of various services.

The project is 100% South African-owned. The project owners comprise IDEAS Fund, managed by Old Mutual; Reatile Solar Power; Phakwe Solar; Business Venture Investments; and the Cicada Community Trust.

The project’s socioeconomic developments will be focused on education, youth development, health, food security and welfare. The programmes have been chosen following research and engagement to ensure that they are well informed and will strengthen the beneficiary communities.

Moreover, a percentage of the revenue generated every year will be committed to implementing enterprise development initiatives to build resilience and accelerate the growth and success of entrepreneurial businesses, ultimately stimulating local economic growth and creating opportunities for the economic participation of previously disadvantaged groups.

The focus is on small and microenterprises designed to enhance growth. To deliver on this objective, the establishment of a local resource centre for use by local small, medium-sized and microenterprises, as well as communities, will support this drive to support development, while the provision of accredited skills training will be provided for startup businesses.

Key Contracts and Suppliers
Enel Green Power (Nxuba, Oyster Bay, Garob, Karusa and Soetwater wind farms); BioTherm Energy (Golden Valley, Excelsior, Konkoonsies II and Aggeneys projects); Goldwind (engineering, procurement and construction, or EPC, contractor – Excelsior and Golden Valley projects); ET Solutions (EPC contractor – Aggeneys and Konkoonsies II projects); Mainstream Renewable Power (Kangnas and Perdekraal wind farms); Concor and Conco (construction contractor – Kangnas and Perdekraal wind farms); Siemens Gamesa Renewable Energy (supply and installation of wind turbines – Kangnas and Perdekraal wind farms); Ngodwana Energy (biomass project); ELB Engineering Services, KC Cottrell and the ELB Educational Trust (EPC contractor – Ngodwana Energy biomass project); Building Energy and G7 Renewable Energies (Roggeveld Wind Farm); Nordex (wind turbines – Roggeveld, Nxuba, Copperton and Garob wind farms); Scatec Solar (Sirius Solar, Dyason’s Klip 1 and Dyason’s Klip 2 solar PV projects); Innowind (Wesley-Ciskei wind farm); Elawan Energy (Copperton, Roggeveld, Karusa, Nxuba and Golden Valley wind farms and Redstone CSP); Acwa Power SolarReserve Redstone Solar Thermal Power Plant (Redstone CSP); Solar Capital (Loeriesfontein Orange solar PV project); IDEAS Fund, managed by Old Mutual; Reatile Solar Power; Phakwe Solar; Business Venture Investments; and the Cicada Community Trust (Bokamoso Wind Farm).

juwi Renewable Energies (EPC and operation and maintenance contracts – Waterloo, Bokamoso and Droogfontein 2 solar parks); Old Mutual Life Assurance Company and AECD (Droogfontein 2 and Zeerust solar parks) and GRS (Greefspan PV Power Plant Number Two solar park).

Contact Details for Project Information
DoE departmental spokesperson Thandiwe Maimane, tel +27 12 444 4256, cell +27 82 450 8591, fax +27 86 581 8505 or email MediaDesk@energy.gov.za.

Edited by Creamer Media Reporter

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

An unmanned breathalyser that is made to be tough and simple to use. Can be used in any environment for operator-free breathalyser testing.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.09 0.163s - 167pq - 2rq
Subscribe Now