Renard diamond project, Canada

18th July 2014

  

Font size: - +

Name and Location
Renard diamond project, Quebec, Canada.

Client
Stornoway Diamonds.

Project Description
The Renard diamond project is located about 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau, in the James Bay region of north-central Quebec.

The project hosts probable mineral reserves, as defined under National Instrument 43-101, at 17.9-million carats. The total indicated mineral resources, inclusive of the mineral reserve, are 27.1-million carats, with a further 16.9-million carats classified as inferred mineral resources, and 25.7-million carats to 47.8-million carats classified as no-resource exploration upside. All kimberlites remain open at depth.

The November 2011 feasibility study included ramp and shaft access to the Renard underground mine. According to the optimisation study released in January 2013, shaft sinking will now be deferred until later in the mine life and access to the underground mine will be through a ramp only.

The shaft will be developed to a depth of 610 m, sufficient to extract all mineral reserves and the inferred mineral resources. It will also be enlarged to accommodate the planned production rate of 6 000 t/d of ore. Ore will be hauled to surface by 60 t trucks, with ramp ventilation capacity and surface maintenance facilities expanded to accommodate the increased fleet. Plant capacity remains at 6 000 t/d, expandable to 7 000 t/d. Power requirements are expected to total 12.2 MW during operations, provided through on-site diesel power generation.

According to the optimisation study, diamond production in years 1 and 2 will be derived predominantly from the Renard 2/3 openpit. Diamond production from the underground mine will start during year 2. As indicated in the feasibility study, underground ore will be mined, with blast-hole shrinkage on the 250 m, 430 m and 610 m development levels and waste backfill from surface. The optimisation study contains a refined draw-point design and a mining sequence incorporating a panel-retreat method to better ensure geomechanical stability and mitigate the unexpected onset of natural caving.

Value
As a result of design changes to the project, preproduction capital costs are estimated at C$752-million, a reduction of C$50-million from the previous estimate.

Duration
First production is expected in the second quarter of 2017.

Latest Developments
Stornoway turned the first sod at the project site on July 10.

This follows the company’s decision to build the Renard diamond project after closing the project’s comprehensive C$946-million financing package.

The project is expected to declare commercial production on schedule during the second quarter of 2017, based on first plant commissioning in late 2016.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The cost of the project has been reduced by C$50-million. Plant commissioning has been postponed by six months.

Contact Details for Project Information
Stornoway Diamonds director of investor relations Orin Baranowsky, tel +1 416 304 1026 ext 103or email info@stornowaydiamonds.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Roytec Global (Pty) Ltd
Roytec Global (Pty) Ltd

Roytec Global is an international company specializing in liquid / solid and mineral separation technologies for the Mining and Industrial sectors.

VISIT SHOWROOM 
Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.071 0.807s - 147pq - 2rq
Subscribe Now