Pueblo Viejo life-of-mine extension project, Dominican Republic – update

15th April 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Pueblo Viejo life-of-mine extension project.

Location
Sanchez Ramirez pro­vince, in the Dominican Republic.

Project Owner/s
Barrick Gold, in a 60:40 joint venture with Newmont Corporation.

Project Description
The project aims to advance a plant expansion and tailings storage facility (TSF).

The new TSF will allow for operations to continue beyond 2040 at an average of 800 000 oz/y of gold.

Potential Job Creation
The company’s workforce, which is 97% Dominican, is expected to increase as the project develops, consequently increasing opportunities for women to participate.

It will also promote the development of the local economy based on the mine’s suppliers and contractors.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The capital cost of expanding the Pueblo Viejo mine increased from $1.3-billion in March 2020 to $1.4-billion in March 2022.

Planned Start/End Date
The project was approved to proceed in March 2020 and is expected to be completed by the end of 2022.

Latest Developments
The strategic review of the location of the TSF has been completed, paving the way for Barrick Gold to progress the project.

Government and Barrick Gold have separately studied sites for the TSF location, with the assessments independently identifying four alternative sites, two of which, in the Sanchez Ramirez province, will be proposed for further investigation.

Barrick president and CEO Mark Bristow has noted that, although these alternative sites existed as determined by the reviews, the final location and construction of the facility will be subject to the completion of an environmental- and social-impact assessment (ESIA).

The ESIA will be submitted to the Dominican government for evaluation and final decision.

Barrick has stated that it is committed to following international standards and will adhere to the Global Industry Standard on Tailings Management in terms of design, construction, operation and closure of the TSF.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Barrick Gold Corporation investor and media relations, Kathy du Plessis, tel +44 20 7557 7738 or email barrick@dpapr.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.049 0.979s - 127pq - 2rq
Subscribe Now