Name of the Project
Pilbara gold project.

Location
Australia.

Project Owner/s
De Grey Mining.

Project Description
A scoping study on the project has shown a positive cash flow outcome based on a baseline one-million-tonne-a-year throughput and the establishment of a purpose-built one-million-tonne-a-year carbon-in-leach (CIL) plant.

A sulphide flotation and regrind circuit is proposed to be added in Year 3. 

The project envisages gold production of about 290 000 oz over five years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The project has an initial Stage 1 capital estimate of $78-million, including a 15% contingency. The capital cost to establish the Stage 2 sulphide flotation circuit is estimated at $18-million (funded through cash flow) and is planned to be operational in Year 3.

Planned Start /End Date
Not stated.

Latest Developments
De Grey Mining is considering doubling the scale of its Pilbara gold project on the back of an increase in the resource estimate.

The company has told shareholders that the scale of the development study will be increased to a two-million-tonne-a-year plant throughput, up from the one-million tonnes a year considered in the 2017 scoping study.

Preliminary economic evaluations have shown that the increased scale should result in a production profile of more than 100 000 oz/y of gold, up from the previous estimate of between 51 000 oz/y and 65 000 oz/y.

De Grey has noted that the decision to increase the proposed scale of the Pilbara project is also supported by the improved gold price outlook, economies of scale and a simplified process plant flowsheet.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
De Grey Mining, tel +61 8 9381 4108, fax +61 8 9380 6761 or email admin@degreymining.com.au.

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.079 0.89s - 147pq - 2rq
Subscribe Now