Perkoa joint venture project, Burkina Faso
Name and Location
Perkoa joint venture (JV) project, Burkina Faso.
Client
The project is a JV between Blackthorn Resources (39.9%) and Glencore International (50.1%), with the remainder being held by the government of Burkina Faso (10%).
Project Description
The project involves the development of the first zinc mine in West Africa.
The project is located within the Proterozoic Boromo greenstone belt, about 120 km west of Burkina Faso’s capital, Ouagadougou.
In May 2012, the Perkoa JV announced mineral resources of 12.17-million tons at 10.3% zinc and 53.9 g/t silver at the Perkoa project, including measured and indicated mineral resources of 7.15-million tons at 11% zinc and 53.8 g/t silver.
Further, Blackthorn approved participation in a proposal by Glencore to upgrade the project, including:
• Extraction of silver and lead concentrate in a separate processing circuit by bulk mining the hanging-wall zone of the deposit;
• Opencut mining of near-surface mineralisation, situated along strike and adjacent to the underground mining area; and
• Increased throughput of the processing plant from 720 000 t/y to 1-million tons a year.
Value
Glencore previously agreed to provide development capital of $120-million to fund the expanded project construction and commissioning through a combination of project equity and project loans. In addition, Glencore agreed to provide or source a maximum working capital facility of $20-million, for a total financing package of $140-million.
However, the revised estimate of costs up to completion of commissioning provided by Glencore to the JV is now expected to be $180-million. This amount includes costs relating to project construction, capacity expansion, underground and open-cut development and the addition of a lead and silver circuit, as well as the accumulation of working capital to the completion of commissioning.
This revised estimate brings the total cost of the project to the end of commissioning, including Blackthorn Resources’ initial $80-million capital spend, to an estimated $260-million.
In addition to the increased costs to complete commissioning, further short-term funding will also be required in the first year of production to cover revised capital and working capital estimates that are not yet finalised.
The JV partners are collaborating on budget optimisation to minimise future short-term working capital requirements. It is expected that the final budget will be agreed upon with Glencore in February 2013.
Duration
Commissioning is expected to be completed by the end of February 2013 and the first export vessel is expected to sail during the second quarter.
Latest Developments
The Perkoa project was officially opened on January 19, 2013.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
The cost of the project has escalated from $140-million to $180-million.
Contact Details for Project Information
Blackthorn Resources, tel +226 50 31 66 35, fax +226 50 31 70 97 or email info@blackthornresources.com.au, or MD Scott Lowe, tel +61 2 9357 9000.
Glencore International, tel +41 41 709 2000, fax +41 41 709 3000 or email info@glencore.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation