Pebble copper/gold/molybdenum project, US
Name of the Project
Pebble copper/gold/molybdenum project.
Location
South-west Alaska, US.
Project Owner/s
Pebble Limited Partnership (PLP), wholly owned by Northern Dynasty Minerals.
Project Description
The Pebble project is the world’s largest undeveloped copper and gold resource. The project’s tonnes, grade, metallurgy and geometry have the potential to support a modern, long-life mine.
The project’s current resource estimate includes 6.44-billion tonnes in the measured and indicated categories containing 57-billion pounds of copper, 70-million ounces of gold, 3.4-billion pounds of molybdenum and 344-million ounces of silver. The inferred category of 4.46-billion tonnes contains 24.5-billion pounds of copper, 37-million ounces of gold, 2.2-billion pounds of molybdenum and 170-million ounces of silver. The deposit also contains palladium and rhenium.
The PLP is proposing to develop the Pebble copper/gold/molybdenum porphyry deposit as an openpit mine, with associated on- and off-site infrastructure including:
• a 230 MW power plant located at the mine site,
• a 134 km transport corridor from the mine site to a port site on the west side of Cook Inlet,
• a permanent, year-round port facility near the mouth of Amakdedori Creek on Cook Inlet and
• a 303 km natural gas pipeline from the Kenai Peninsula to the Pebble project site.
The proposed mine will operate for about 20 years. This includes 14 years of mining using conventional drill-blast-shovel operations, followed by six years of milling material from a low-grade-ore (LGO) stockpile. The mining rate will average 90-million tons a year, with 58-million tons of mineralised material being processed through the mill each year for an extremely low life-of-mine waste-to-ore ratio of 0.1:1.
Mine site facilities will include an openpit mine, tailings storage facilities (TSFs), an LGO stockpile, overburden stockpiles, quarry sites, water management ponds, milling and processing facilities, as well as supporting infrastructure such as the power plant, water treatment plants, camp facilities and storage facilities.
The openpit will be developed in stages and will eventually be 1 981 m long, 1 676 m wide and between 405 m and 533 m deep. A total of 1.2-billion tons of material will be mined, including 1.1-billion tons to be processed through the mill and 100-million tons of waste rock.
Nonpotentially acid-generating (non-PAG) waste rock will be used as a construction material for on-site roads and TSFs embankments.
A small amount of waste rock considered non-PAG will be stored in a lined LGO stockpile until mine closure, at which time it will be back-hauled to the openpit for permanent subaqueous storage.
Mineralised material will be processed using conventional froth flotation. On average, the process plant will produce about 600 000 t/y of copper/gold concentrate containing an estimated 287-million pounds of copper, 321 000 oz of gold and 1.6-million ounces of silver, and 15 000 t/y of molybdenum concentrate containing about 13-million pounds molybdenum.
A TSF, located in the North Fork Koktuli drainage, will store 1.1-billion tons of tailings generated over 20 years of mine operations. About 88% will be non-PAG bulk tailings; the remaining 12% will be pyritic PAG tailings, which will be stored subaqueously in a separate, fully lined cell within the TSF. Four TSF embankments, ranging from 18.3 m (east embankment) to 183 m (main embankment) in height, will be developed, with centre-line or downstream construction methods used for all external embankments. A conservative 2.6:1 (horizontal:vertical) slope is targeted to ensure safety and stability under all operating conditions, including maximum possible flood and seismic events.
Potential Job Creation
The Pebble project will directly employ about 2 000 workers during its four-year construction phase and an estimated 850 workers during its 20-year operations phase.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Capital expenditure on Pebble is estimated at between $6-billion and $8-billion.
Planned Start /End Date
Not stated.
Latest Developments
The PLP has finalised a right-of-way agreement with Iliamna Natives, securing the right to use defined portions of its lands for the construction and operation of transportation infrastructure associated with the Pebble project.
Iliamna Natives is an Alaska Native village corporation with extensive land holdings proximal to the Pebble site, in south-west Alaska, and represents more than 150 native shareholders, many of whom live in the nearby village of Iliamna.
The right-of-way agreement with Iliamna Natives is the second such agreement the PLP has reached with Native landowners to secure access to the project site for construction and operation of the proposed mine. A similar agreement was reached with Alaska Peninsula, a village corporation with land holdings north and south of Lake Iliamna, last November.
PLP president and CEO Tom Collier says more partner announcements with Alaska Native corporations will be announced this year.
Key Contracts and Suppliers
Wardrop Engineering (preliminary assessment report).
On Budget and on Time?
The Pebble deposit has inspired intense controversy, as a broad and bipartisan coalition – including environmentalists, Alaska natives and commercial fishermen – has fought its planned development, resulting in the EPA stopping the project in 2014. The election of US President Donald Trump, however, has fuelled hopes that a more mining-friendly EPA will enable the project to progress.
Contact Details for Project Information
PLP, tel +1 907 339 2600, fax +1 877 450 2600 or email receptionist@pebblepartnership.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation