PERTH (miningweekly.com) - Gold miner PanTerra Gold on Tuesday reported that its processing plant at the Las Lagunas project, in the Dominican Republic, was now running at its design capacity of 100 t/h.

During November last year, the miner halved production at Las Lagunas after experiencing mechanical issues with the ball mill.

A replacement ball mill motor has now been installed, with the mill handling the grind of coarser refractory tailings from the Pueblo Viejo mine, currently being fed into the plant. PanTerra noted that the existing motor, which was still under warranty, would be rewound so as to achieve nameplate capacity and then serve as a spare.

With the regrind section of the process plant now operating to design capacity, the technical team could concentrate on fine-tuning the three other circuits to optimise gold and silver recoveries, the company said.

Meanwhile, PanTerra was also investigating the prospects of claims for compensation against several suppliers, as expected income for the past six months had been significantly reduced as a result of the design and manufacturing issues experienced.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.047 0.947s - 140pq - 2rq
Subscribe Now